Questions # 41:

What is documented in the project plan to support the 'manage by exception' principle?

Options:

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Questions # 42:

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of ‘business case management technique should this be considered?

Options:

A.

Develop

B.

Check

C.

Maintain

D.

Confirm

Questions # 43:

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

Options:

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Questions # 44:

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions # 45:

Which is a purpose of the quality theme?

Options:

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Questions # 46:

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

Options:

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Questions # 47:

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

Options:

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Questions # 48:

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Questions # 49:

Which is a responsibility of the project board?

Options:

A.

To manage the team managers and project support

B.

To ensure production of the project's outputs

C.

To ensure effective communication with external stakeholders

D.

To implement the change control approach

Questions # 50:

Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

Options:

A.

project assurance

B.

the project board

C.

the corporate, programme management or the customer

D.

a team manager