Questions # 11:

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

Options:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Questions # 12:

Could a user with Access Control List (ACL) authorization ‘Read’ lock a project?

Please choose the correct answer.

Response:

Options:

A.

Yes

B.

No

Questions # 13:

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?

Please choose the correct answer.

Response:

Options:

A.

Internally-processed activities

B.

Externally-processed activities

C.

Service activities

D.

Scheduled activities

Questions # 14:

With reference to WBS scheduling, which of the following statements are FALSE?

Please choose the correct answer.

Response:

Options:

A.

In WBS scheduling, the activities which are assigned to the selected WBS elements are scheduled. In network scheduling on the other hand, all activities which belong to the network are scheduled.

B.

If you selected scheduling type 'WBS determines dates', the earliest start date of the activities is defaulted from the respective WBS elements in case of forward scheduling (or the latest finish date of the activities in case of backward scheduling).

C.

The execution of WBS scheduling consists of 2 steps: 1. Determining the initial dates (start dates for forward scheduling or finish dates for backward scheduling). 2. Transferring the dates of the activities into respective network headers and WBS elements.

D.

Activities which are not scheduled, but have relationships to activities involved in scheduling, are viewed as external activities. In this case, the dates of the external activity are taken into account as restricting dates.

Questions # 15:

Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?

Please choose the correct answer.

Response:

Options:

A.

Manual planning in billing elements in the project structure

B.

Sales order planning

C.

Billing plan in project billing elements

D.

Hierarchical billing plan

Questions # 16:

In internal processing which views allow you to easily and quickly assign persons to activities and use various data (availability of the person from Human Resources, the total work planned for that person, or the activity date)?

There are 2 correct answers to this question.

Response:

Options:

A.

Project view

B.

Resource view

C.

Work center view

D.

Assignment view

Questions # 17:

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

This assignment can then be used to display the planned costs of the orders of the project

B.

This assignment can then be used to display the unit costs of the orders of the project

C.

It can be copied to a new project

D.

Cost planning can be moved automatically along with the activities

Questions # 18:

Which of the following cost planning transactions are related to Account assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

Invoice posting

B.

Goods movement

C.

Confirmations

D.

Purchase requisitions

Questions # 19:

Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned?

There are 3 correct answers to this question.

Response:

Options:

A.

Persons

B.

Organizational units

C.

Jobs

D.

Positions

Questions # 20:

Which of the following aids in calculating actual overheads based on the costing sheet and overhead key entered?

There are 3 correct answers to this question.

Response:

Options:

A.

WBS element

B.

Assignment

C.

Network header

D.

Network activity