Questions # 21:

What are the prerequisites for automatic requirements grouping on the top WBS element of a project?

There are 2 correct answers to this question.

Response:

Options:

A.

The "project stock" indicator is set in the project definition (either valuated or non-valuated)

B.

The "Valuated project stock" indicator must be set in the project definition.

C.

The MRP group of the components must permit requirements grouping.

D.

The project must be released.

E.

The top-level WBS element must be released.

Questions # 22:

Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling of subnetworks and subordinate internal orders

B.

Introduction of a configurable level concept for the targeted selection of

C.

Scheduling that takes available capacities and material availability into

D.

Improve performance through the targeted selection of subnetworks to be

E.

Detailed subnetwork monitor

Questions # 23:

How do you create a detailed payment schedule if the expense for an external activity or purchased component is not paid with a single invoice?

Please choose the correct answer.

Response:

Options:

A.

Invoicing plan

B.

Billing plan

C.

Credit memos

D.

Detailed billing plan

Questions # 24:

Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors?

Please choose the correct answer.

Response:

Options:

A.

Work center and planned work

B.

Work center and activity

C.

Activity and task

D.

Work center and vendor

Questions # 25:

Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials?

Please choose the correct answer.

Response:

Options:

A.

Operative network

B.

Task network

C.

Standard network

D.

Internal network

Questions # 26:

Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:

Options:

A.

Partially released

B.

Released

C.

Partially set

D.

Partially finished

Questions # 27:

Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks.

How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time?

Please choose the correct answer.

Response:

Options:

A.

Safety measures

B.

Status management

C.

Claim management

D.

Actions

Questions # 28:

Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?

Please choose the correct answer.

Response:

Options:

A.

Costing variant

B.

Valuation variant

C.

Planned cost variant

D.

Network variant

Questions # 29:

Based on which of the following the checking control function determines whether an order type will be checked and if so, which checking rules should be used?

Please choose the correct answer.

Response:

Options:

A.

Status

B.

Scope

C.

Group

D.

Check indicator

Questions # 30:

In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.

How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

Please choose the correct answer.

Response:

Options:

A.

The costs are distributed evenly over the earliest dates in the activity

B.

The system uses the key from the work center

C.

System uses valuation variant

D.

Costing key is considered