Questions # 31:

Which of the following decides whether networks can be header assigned or activity-assigned?

There are 2 correct answers to this question.

Response:

Options:

A.

Order type

B.

Plant

C.

Billing type

D.

Network structure

Questions # 32:

Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile?

Please choose the correct answer.

Response:

Options:

A.

Proj.summ.master data indicator

B.

Project summarization indicator

C.

Capacity requirement indicator

D.

Version profile indicator

Questions # 33:

Project System has its own Organizational structure, which can be a matrix structure.

Please choose the correct answer.

Response:

Options:

A.

True

B.

False

Questions # 34:

How can the capacity requirements of an activity be reduced?

There are 3 correct answers to this question.

Response:

Options:

A.

With partial confirmations of the activity

B.

By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)

C.

With the period-end closing

D.

By setting the status locked account assignment

E.

With the final confirmation of the activity

Questions # 35:

What are the three tables that are defined for order type in network costing?

There are 3 correct answers to this question.

Response:

Options:

A.

Each order type

B.

Each order type and plant

C.

Network profile

D.

Each plant

Questions # 36:

What is copied when transferring a simulation version back to an operative project?

There are 3 correct answers to this question.

Response:

Options:

A.

Plan costs

B.

WBS elements

C.

Actual work

D.

Maintenance orders assigned to the project

E.

Network activities

Questions # 37:

In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?

There are 2 correct answers to this question.

Response:

Options:

A.

Network overview

B.

Order overview

C.

Structure overview

D.

Project structure overview

Questions # 38:

Which of the following items can be included in the planned costs for an activity besides the cost of the activity?

There are 3 correct answers to this question.

Response:

Options:

A.

Activity elements

B.

Overheads determined through overhead costing sheet

C.

Process costs determined through a process template

D.

Material management cost

Questions # 39:

Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?

Please choose the correct answer.

Response:

Options:

A.

Overheads costing

B.

Planned costing

C.

Profitability costing

D.

Activity based costing

Questions # 40:

For which objects can billing plans be created? (2)

Options:

A.

Activities

B.

Sales order items

C.

WBS elements

D.

Milestones

E.

Project definition