Viewing page 2 out of 3 pages
Viewing questions 11-20 out of questions
Questions # 11:

If the client has purchased green power that is not Green-e certified, then the project team should

Options:

A.

accept not earning Energy and Atmosphere Credit, Green Power

B.

provide documentation as to how the green power is equivalent to Green-e certified

C.

apply for an Innovation Credit and explain the situation in a narrative

D.

apply the percentage to Energy and Atmosphere Credit, Renewable Energy Generation

Questions # 12:

A 1,500 ft2 (139 m2) mobile home is built in the downtown area of a major city. 90% of the project's gross floor will be

completed by the time of occupancy. LEED certification is being sought. Which rating system would be the most

appropriate one to use?

Options:

A.

LEED Interior Design and Construction

B.

LEED Building Design and Construction

C.

LEED for Homes

D.

No rating system

Questions # 13:

During value engineering a project team is looking to see if they can reduce the number of thermal comfort controls. The project's LEED AP notices there are thermostats in the public restroom and says they can be eliminated because public restrooms are considered

Options:

A.

unoccupied space

B.

densely occupied space

C.

shared multioccupant space

D.

nonregularly occupied space

Questions # 14:

The Commissioning Authority (CxA) must report results, findings and recommendations directly to the

Options:

A.

owner

B.

architect

C.

contractor

D.

project manager

Questions # 15:

Which sentence is true about Renewable Energy Certificates (RECs)?

Options:

A.

RECs can be used to mitigate the effects of all scope two emissions.

B.

RECs can be used toward both electric and nonelectric energy use.

C.

RECs can be used to mitigate emissions from purchased electricity.

D.

RECs can be used to mitigate emissions from electricity produced on site.

Questions # 16:

In a goal-setting workshop, a decision is made to place circulation at the exterior of the office perimeter next to the window wall. Which of the following is an example of integrated decision-making?

Options:

A.

Installing blinds to increase occupant comfort

B.

Darkening the color of the carpet along the perimeter to aid way-finding

C.

Lowering the heating set-point in the circulation space to conserve energy

D.

Issuing user guidelines which limit the height of occupant additions to cubicles along the perimeter

Questions # 17:

What percentage of occupants require individual control of thermal systems under Indoor Environmental Quality, Thermal Comfort?

Options:

A.

25%

B.

50%

C.

75%

D.

90%

Questions # 18:

Which strategy could be incorporated into the negotiations of a lease agreement between a tenant and building owner

to contribute towards earning a LEED credit?

Options:

A.

A lease renewal option prior to 10 years

B.

Discounted parking fees for first year of lease

C.

An energy payment plan where the tenant pays a flat rate on utilities through the building owner

D.

Energy purchase through the building owner's campus facility that produces renewable power to Green-e standards

Questions # 19:

A photovoltaic (PV) system was installed after commissioning (Cx) was completed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?

Options:

A.

No action is necessary as the PV system is not required to be commissioned

B.

The PV system installer should commission their own installations and share the results with the project owner

C.

The building's electrical engineer should commission the installation and share the results with the project owner

D.

The Cx agent for the project must return and conduct or oversee the commissioning of the PV system

Questions # 20:

Which of the following appliances are included in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Commercial dishwashers and coffee makers

B.

Residential clothes washers and dishwashers

C.

Residential dishwashers and drinking fountains

D.

Commercial clothes washers and coffee makers