Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the USGBC Leadership in Energy and Environmental Design (LEED) LEED-AP-ID+C Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam LEED-AP-ID+C Premium Access

View all detail and faqs for the LEED-AP-ID+C exam


667 Students Passed

95% Average Score

97% Same Questions
Viewing page 3 out of 3 pages
Viewing questions 21-30 out of questions
Questions # 21:

A project has performed an energy model which has resulted in the following energy end use consumption:

Question # 21

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2. Advanced Metering, energy meters must be installed for energy end uses in

Options:

A.

space cooling, interior fans and receptacles

B.

interior lighting, space heating, space cooling and interior fans

C.

interior lighting, space heating, space cooling, interior fans and receptacles

D.

exterior lighting, interior lighting, space heating, space cooling, interior fans, service water heating and receptacles

Questions # 22:

A tenant moves into an existing building where no modifications to the building envelope will be made. What credit would be affected by the visible light transmittance of the existing exteriorglazing?

Options:

A.

Indoor Environmental Quality Credit, Daylight

B.

Indoor Environmental Quality Credit, Quality Views

C.

Materials and Resources Credit, Interiors Life-Cycle Impact Reduction

D.

Energy and Atmosphere Credit, Fundamental Commissioning and Verification

Questions # 23:

In addition to the Material Type, what other information needs to be included in the Construction and Demolition Waste Management Calculation?

Options:

A.

Waste stream, total waste, diverted waste, waste to landfill

B.

Waste volume, commingled waste, wood for energy, reused items

C.

Donated waste, landfill waste, percentage of cardboard with recycled content, diverted waste

D.

Percentage of alternative daily cover (ADC) produced by the sorting facility, total of donated items, total of wood recycled, total of wood reused

Questions # 24:

A mechanical engineer needs to identify spaces that are considered densely occupied according to LEED in order to document

Options:

A.

Indoor Environmental Quality Credit, Interior Lighting, Option 2

B.

Indoor Environmental Quality Credit, Thermal Comfort, Control Requirements

C.

Indoor Environmental Quality Credit, Indoor Air Quality Assessment, Option 2. Air Testing

D.

Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies, Option 2 C. Carbon Dioxide Monitoring

Questions # 25:

The project architect suggests reducing the area planned for surface parking and replacing it with additional green space. What benefit would this strategy provide to the owner?

Options:

A.

Increase the rainwater infiltration capacity

B.

Decrease the amount of bicycle parking that must be provided

C.

Increase the overall SR (solar reflectance) of the hardscape area

D.

Decrease the required amount of on-street parking that must be provided

Questions # 26:

Using the scale of 0 = no view and 5 = maximum view, what is the view factor in the diagram below, as defined in Indoor Environmental Quality Credit, Quality Views?

Question # 26

Options:

A.

View Factor 1

B.

View Factor 2

C.

View Factor 4

D.

View Factor 5

Questions # 27:

After the construction and installation of all finishes and furnishing of a new 36,000 ft2 (3 344.5m2) office space, what is the minimum total volume of outdoor air that is required during a non-phased flush-out procedure to achieve Indoor Environmental Quality Credit, Indoor Air Quality Assessment?

Options:

A.

126,000,000 ft3 (3 567 922.7 m3)

B.

378,000,000 ft3 (10 703 768.1 m3)

C.

504,000,000 ft3 (14 271 690.7 m3)

D.

522,000,000 ft3 (14 781 394.0 m3)

Questions # 28:

Based on the results of a six-hour waste stream study, the team for an Interior Design and Construction Retail project plans to provide dedicated areas for four recyclable waste streams: cardboard, plastic, metal, and paper.

The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?

Options:

A.

Take appropriate measures for the safe collection, storage and disposal of batteries

B.

Make a waste stream projection for the entire year based on the six hours of the waste stream study

C.

Make a waste stream projection for the entire week, based on the six hours of the waste stream study

D.

Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Questions # 29:

Drywall is purchased from a local manufacturer for a total materials cost of $10,000 USD. The specification of the drywall is:

· 5% of the product is comprised of post-consumer recycled paper sourced from a pulp mill 25 mi. (40 km) away;

· 50% of the product is post-consumer recycled gypsum attained from a facility 30 mi. (48 km) away;

· new gypsum is extracted from a mine 175 mi. (282 km) away.

What is the contributing value of the drywall to Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

Options:

A.

$5,500 USD

B.

$9,750 USD

C.

$11,000 USD

D.

$19,500 USD

Questions # 30:

To determine the area of interior nonstructural elements, the LEED AP will include which one of the following in the calculation for Materials and Resources Credit, Interiors Life Cycle Impact Reduction, Option 1. Interior Reuse?

Options:

A.

Up to three layers of a floor assembly

B.

Items that are demolished and not replaced

C.

The interior side of exterior windows and doors

D.

Hazardous materials that are remediated as part of the project