Questions # 101:

Which of the following does not require the WBS as an input?

Options:

A.

Activity definition

B.

Cost estimating

C.

Negotiation

D.

Resource planning

Questions # 102:

Which of the following contract types is described in the statement below?

"This contract type provides no incentive for the contractor to control costs and hence is rarely utilized."

Options:

A.

Cost Plus Fixed Fee

B.

Cost Plus Award Fee

C.

Cost Plus Percentage of Cost

D.

Cost Plus Incentive Fee

Questions # 103:

You work as a project manager for PassGuide Inc. Which of the following charts provides a useful framework that helps you in deciding which risks need your attention?

Options:

A.

Gantt chart

B.

Risk probability and impact matrix

C.

Pareto chart

D.

Scatter chart

Questions # 104:

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?

Options:

A.

Expert Judgment

B.

Make or buy analysis

C.

Survey Questionnaire

D.

Issue log

Questions # 105:

In which of the following contract types, the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment which is calculated as a percentage of the initial estimated project costs?

Options:

A.

Communications Management Plan, Execution Process group

B.

Communications Management Plan, Planning Process Group

C.

Project Management Plan, Planning Process Group

D.

Project Management Plan, Initiating Process Group

Questions # 106:

You work as a project manager for PassGuide Inc. You are performing a task to generate a hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?

Options:

A.

PERT chart

B.

WBS

C.

RBS

D.

Gantt chart

Questions # 107:

Jane works as a project manager for PassGuide Inc. Various projects are running under her administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?

Options:

A.

Holly's project is ahead of the schedule.

B.

Holly's project is behind the schedule.

C.

Holly's project has costs that are higher than planned.

D.

Holly's project is right on target.

Questions # 108:

You are the project manager of a computer upgrade project. You and the vendor are in dispute over the deliverables the vendor was to provide and configure. What document can best describe how you and the vendor are to proceed if there is a claim against the vendor?

Options:

A.

Procurement management plan

B.

Project cost management plan

C.

Enterprise environmental factors

D.

Contract

Questions # 109:

Which of the following refers to the transmission of a message from one person to another in a simple triangle consisting of the context, the sender, the message, and the receiver?

Options:

A.

Communication

B.

Crisis

C.

Collaboration

D.

Compromise

Questions # 110:

Mark works as a project manager for PassGuide Inc. You have to monitor the status of the project and product scope. Which of the following processes will you use to accomplish the task?

Options:

A.

Create WBS

B.

Define Scope

C.

Verify Scope

D.

Control Scope