Questions # 81:

You work as a project manager for PassGuide Inc. You have to subdivide project deliverables and project work into smaller, more manageable components. Which of the following processes will you use to perform the above task?

Options:

A.

Create WBS

B.

Control scope

C.

Verify scope

D.

Define activities

Questions # 82:

Which of the following are inputs of the Perform Quality Control process?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Project management plan

B.

Quality metrics

C.

Quality checklists

D.

Validated changes

Questions # 83:

You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Options:

A.

0.87

B.

0.84

C.

0.86

D.

0.80

Questions # 84:

You are the owner of a company that handles accounting operations for all its clients. Recently, your clients have been complaining about inefficiency of your business processes, and the lack of productivity. You want to put in place an initiative with the team, which will review the processes and make recommendations for improvement on an on-going basis, which you can use. What kind of management would this team need?

Options:

A.

Program Management

B.

Portfolio Management

C.

Business Process Management

D.

Project Management

Questions # 85:

You work as a project manager for PassGuide Inc. You have to complete and settle each contract, including the resolution of any open items, and close each contract applicable to the project or a project phase. Which of the following processes will help you to accomplish the task?

Options:

A.

Report Performance

B.

Perform Quality Control

C.

Close Procurements

D.

Close Project or Phase

Questions # 86:

Which of the following process groups starts after the planning phase of a project is over?

Options:

A.

Monitoring and Controlling

B.

Initiation

C.

Testing

D.

Execution

Questions # 87:

Which of the following calculates the earliest and latest starts and finishes of each activity without making the project longer?

Options:

A.

RACI

B.

RBS

C.

CPM

D.

WBS

Questions # 88:

You work as a project manager for PassGuide Inc. You want to communicate and solicit feedback from your employees to build future plans. Which of the following will help you to accomplish the above task?

Options:

A.

Stakeholders register

B.

Risk register

C.

Organizational chart

D.

Change register

Questions # 89:

Which of the following skills includes vision, gaining consensus for strategic goals, and establishing direction?

Options:

A.

Organizational skill

B.

Budgeting skill

C.

Negotiation and Influencing skill

D.

Leading skill

Questions # 90:

Which of the following contracts is generally considered to be the most risky for the buyer?

Options:

A.

Cost plus percentage of costs

B.

Cost plus incentive fee

C.

Time and materials

D.

Fixed fee