Questions # 61:

Which of the following types of organizations reduces duplication of work because responsibilities are clearly defined on a company-wide basis?

Options:

A.

Matrix

B.

Jury

C.

Functional

D.

Projectized

Questions # 62:

Fill in the blank with the appropriate term.

______is the measure of chance that, due to unfavorable events, the planned or budgeted cost of events can be exceeded

Options:

Questions # 63:

Which of the following techniques is described in the statement below?

"It is an early warning project management tool that allows managers to discover and control errors before they become unmanageable."

Options:

A.

Resource leveling

B.

Earned Value Analysis

C.

What-if scenario analysis

D.

Variance analysis

Questions # 64:

You are the project manager for your organization. The resources that you'll be using on your project are part of a union. The union representatives inform you that you may only utilize union labor on your project for a maximum of 25 hours per week. What approach will you need to do to reveal over utilization of the union resources?

Options:

A.

Critical path method

B.

Fast tracking

C.

Critical chain method

D.

Resource leveling

Questions # 65:

Which of the following techniques is used for weather forecasting?

Options:

A.

Probabilistic forecasting

B.

Scenario building

C.

Simulation

D.

Delphi method

Questions # 66:

You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Procurement

Questions # 67:

Fill in the blank with the appropriate term.

A _______ is a scale of values for the vendors where not all of the values are of the same weight

Options:

Questions # 68:

Which of the following are the types of casual/econometric forecasting methods?

Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Scenario building

B.

ARIMA

C.

ARMA

D.

Econometrics

Questions # 69:

Mark works as a project manager for the SLQ Project. He is working with the project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique will Mark use to achieve the above task?

Options:

A.

Predecessor and successor diagramming

B.

System or process flow chart

C.

Influence diagram

D.

Cause and effect diagram

Questions # 70:

Which of the following is the delay between tasks that have a dependency?

Options:

A.

Fixed time

B.

Lead time

C.

Mean time

D.

Lag time