Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PMP Premium Access

View all detail and faqs for the PMP exam


808 Students Passed

91% Average Score

98% Same Questions
Viewing page 2 out of 6 pages
Viewing questions 11-20 out of questions
Questions # 11:

A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.

What can the project manager do to demonstrate the feature integration?

Options:

A.

Involve business stakeholders in the iteration retrospective.

B.

Include the business stakeholders in the iteration review.

C.

Review the backlog in detail with the business stakeholders.

D.

Create a task for the iteration review and add it to the backlog.

Questions # 12:

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

Options:

A.

Cumulative flow diagram

B.

Earned value (EV)

C.

Burndown chart

D.

Forecast estimation

Questions # 13:

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.

Ensure the client representative is involved in the estimation.

B.

Review the completion costs of similar projects.

C.

Ensure that a 20% contingency is included in the estimation.

D.

Review the lessons learned from similar projects.

Questions # 14:

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?

Options:

A.

Ask the team to raise blockers or impediments in daily meetings.

B.

Prioritize deliverables based on business value and define frequent releases.

C.

Ask the team to challenge the project estimations for a faster delivery.

D.

Prioritize the tasks with high risks to reduce the number of iterations required.

Questions # 15:

A project manager is leading a hybrid project that is building an app for a travel industry startup. Due to unforeseen events, the features and the overall solution will not be useable by many customers due to new travel restrictions.

What should the project manager do first?

Options:

A.

Release the team and help them achieve their potential on a new project.

B.

Ask the organization's management for advice regarding the project's direction.

C.

Assess the environmental changes and recommend a pivot for the project.

D.

Pause the project if business value cannot be reached and collect lessons learned.

Questions # 16:

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

Options:

A.

Find available professionals within the organization to fill the gaps.

B.

Allocate funding for seeking external professionals to fill the gaps.

C.

Determine the possibility for team members to split up the required tasks.

D.

Request additional budget for team training for the missing expertise.

Questions # 17:

As part of its growth strategy, management is providing all of its ongoing projects with junior employees and is requesting experienced team members to mentor them. The experienced employees argue that the mentoring program will not add value to their projects and will limit their ability to deliver.

How should the project manager handle this situation?

Options:

A.

Recommend to management that the junior employees should receive formal training and courses.

B.

Schedule time with all of the project team members since it is the role of the project manager to mentor the team.

C.

Allocate specific time for experienced team members to mentor the junior employees.

D.

Assign an instructor to mentor the junior employees so that the experienced team members can focus on project tasks.

Questions # 18:

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

Options:

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Questions # 19:

An ongoing project with company A is impacted by the recent acquisition of company B. This could affect the current suppliers for the ongoing project.

What should the project manager do next?

Options:

A.

Retain company A's supplier based on the long-term relationship with them.

B.

Consolidate the list of suppliers for companies A and B.

C.

Engage the suppliers of company B to validate the current list of suppliers.

D.

Evaluate the project suppliers of company B for future use.

Questions # 20:

A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?

Options:

A.

Beginning

B.

Resolution

C.

Intensification

D.

Final

Viewing page 2 out of 6 pages
Viewing questions 11-20 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.