Questions # 101:

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

Options:

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.

B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.

C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.

Questions # 102:

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Questions # 103:

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Questions # 104:

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager's response?

Options:

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Questions # 105:

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

Options:

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Questions # 106:

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

Options:

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

Questions # 107:

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Questions # 108:

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.

Understand the customer's perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Questions # 109:

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.

B.

Utilize the cloud wiki to collect the necessary knowledge.

C.

Coordinate with the team and the project stakeholders to collect the knowledge.

D.

Provide just-in-time knowledge to the client, upon request.

Questions # 110:

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

Options:

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Questions # 111:

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Options:

A.

Plan Risk Responses, to outline the possible options to bypass the system performance issue

B.

Perform Qualitative Risk Analysis, to assess the extent of the system performance impact

C.

Monitor Risks, to install system performance monitoring tools and update the risk register

D.

Perform Quantitative Risk Analysis, to outline the details of the system performance issues

Questions # 112:

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

Options:

A.

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Questions # 113:

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

Options:

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

Questions # 114:

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

Options:

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Questions # 115:

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Questions # 116:

The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?

Options:

A.

Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.

B.

Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.

C.

Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.

D.

Ask the sponsor to start a new project to support the existing project and help it meet the original time line.

Questions # 117:

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

Options:

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

Questions # 118:

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Questions # 119:

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

Questions # 120:

A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.

What should the project manager do?

Options:

A.

Ask the team to outline their expectations and confirm with them the approach to use for knowledge transfer.

B.

Organize knowledge-sharing workshops and ask one of the senior team members to facilitate them.

C.

Ensure that formal email communication is used when more information is needed to understand the work done.

D.

Hire a technical writer to document the work completed to date and develop a handover document.

Questions # 121:

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

Options:

A.

Communicated a new delivery date to the customer along with the news about the delay

B.

Disclosed to senior management in confidence, then communicated the delay to the customer

C.

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

Questions # 122:

A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project

stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?

Options:

A.

Propose a hybrid approach and determine which stakeholders will be engaged in each phase of the project.

B.

Follow a predictive approach to reduce the training effort, even though there are incremental deliveries in the project.

C.

Use an adaptive approach, engage the stakeholders who have been exposed to adaptive projects, and train those who have not.

D.

Understand the scope complexity and project magnitude prior to determining which approach to use.

Questions # 123:

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

Questions # 124:

A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.

What should the project manager do?

Options:

A.

Escalate the issue to the project sponsor and seek their immediate intervention.

B.

Assign the unallocated tasks to the functional role and then reallocate when the resources are available.

C.

Assign the unallocated tasks to the project management office (PMO) manager and reallocate when the resources are available.

D.

Ignore the unallocated tasks for now and reallocate when the resources are available.

Questions # 125:

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Options:

A.

Design an updated status report.

B.

Request a meeting with the stakeholder.

C.

Escalate this to the project sponsor.

D.

Forward the project status reports.

Questions # 126:

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall

progress.

What should the project manager do next?

Options:

A.

Capture this in the issue log and escalate it to the project sponsor.

B.

Meet with the stakeholder to understand what is causing the delays.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Discuss the need to influence this stakeholder with the sponsor.

Questions # 127:

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.

Organize a meeting with the team and update the work breakdown structure (WBS).

B.

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.

Start the organization's change control process via a change request.

D.

Communicate with an officer in the environmental protection department to check if it is necessary.

Questions # 128:

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

Options:

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

Questions # 129:

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Question # 129

Options:

Questions # 130:

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

Options:

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Questions # 131:

A project manager is reviewing the lessons learned for an historical project. The review identifies that the client's engineer was adamant that they review all changes, even those not identified in the contract.

How should the project manager deal with this when planning the project?

Options:

A.

Ensure the change management plan highlights this requirement to prevent future issues.

B.

Update the project charter with this information regarding change management.

C.

Update the project risk register to identify this risk and describe how to mitigate the issue.

D.

Talk with the client to ensure they are aware of the change management procedure.

Questions # 132:

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

Options:

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Questions # 133:

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

Options:

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Questions # 134:

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

Options:

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

Questions # 135:

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the

documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

Options:

A.

Create a specific sprint to deliver the project documentation.

B.

Assign a dedicated resource to work on the documentation during the project.

C.

Make documentation a standard part of the definition of done (DoD).

D.

Focus on the documentation after the features are delivered.

Questions # 136:

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

Questions # 137:

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Questions # 138:

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Questions # 139:

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Questions # 140:

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

Options:

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

Questions # 141:

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Questions # 142:

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Questions # 143:

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.

B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.

C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.

D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.

Questions # 144:

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Questions # 145:

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

Options:

A.

Select members for their skill or potential.

B.

Establish the project scope and set clear team objectives.

C.

Set performance standards and direction.

D.

Hold early kick-off meetings and regular weekly meetings.

Questions # 146:

A project manager is managing a project that has a new sponsor who is cutting the budget As a servant leader how should the project manager handle the budget cuts with the team?

Options:

A.

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

B.

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope

C.

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack

D.

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan

Questions # 147:

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.

B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.

C.

Set up an intranet site and allow stakeholders to access the relevant project information.

D.

Divide up the organization among the project team to provide direct project updates.

Questions # 148:

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Questions # 149:

A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

Options:

A.

Reassess the risk log to ensure it is up to date.

B.

Monitor quality metrics to ensure the project continues as planned.

C.

Perform lessons learned to ensure the issue does not happen again.

D.

Schedule a team meeting to review the issue,

Questions # 150:

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

Options:

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Viewing page 3 out of 14 pages
Viewing questions 101-150 out of questions