Questions # 41:

A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.

What should the project manager do?

Options:

A.

Escalate the issue to the board with opportunities to recover the delay as soon as possible.

B.

Work with the product owner and the Scrum team to add 2 weeks to the release schedule.

C.

Work with the product owner and the Scrum team to recover the delay before the last release.

D.

Escalate the issue to the board and plan for the engagement to be terminated.

Questions # 42:

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?

Options:

A.

Encourage the team to participate in a peer evaluation activity by the end of the project.

B.

Introduce the use of time sheets and ask team members to review and submit them regularly.

C.

Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.

D.

Meet with the team together and in one-on-one meetings to set clear, shared targets.

Questions # 43:

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project

kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Options:

A.

Develop a stakeholder-by-stakeholder engagement assessment matrix.

B.

Send a letter to the stakeholders to inform them about the project scope and start date.

C.

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

D.

Identify stakeholder rejection as a risk in the project risk register.

Questions # 44:

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

Options:

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

Questions # 45:

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.

What should the project manager do?

Options:

A.

Refer to the requirements traceability matrix and analyze the requirement.

B.

Analyze the benefits management plan and implement the needed change.

C.

Consult the scope management plan with the customer to understand the gap.

D.

Discuss and agree with the customer to implement the missing requirement.

Questions # 46:

At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.

How should the project manager approach this request?

Options:

A.

Establish a set of objective and measurable performance indicators for evaluating team members and share it with the team.

B.

Ask the project team how they would prefer to be evaluated and use those criteria to share results with HR.

C.

Evaluate the project team members' performance based on whether the completed project fulfills its intended objectives.

D.

Meet with HR at the end of the project and provide a confidential evaluation of every team member's performance.

Questions # 47:

A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?

Options:

A.

Provide the HR review team with the team norms document.

B.

Invite the HR review team to attend one of the daily standup meetings.

C.

Discuss the resource management plan with the HR review team.

D.

Direct the HR review team to the communications management plan.

Questions # 48:

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

Options:

A.

Review the Pareto diagram to identify the source of delays.

B.

Meet with the team in 2 weeks to respond to all of the open tasks.

C.

Consolidate the decision-making authority to remain with the project manager.

D.

Delegate the decision-making authority of some tasks to the team.

Questions # 49:

A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project

manager is confused since the entire team is located in the same time zone and believes there are other factors at play.

What should the project manager do next?

Options:

A.

Rectify ground rule violations.

B.

Review performance formally.

C.

Examine the team's virtual needs.

D.

Implement new options.

Questions # 50:

A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?

Options:

A.

Ask the project team to meet and document why the stakeholder's approach is incorrect.

B.

Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.

C.

Discuss the issue with the project team during a project status meeting and request that they change the approach.

D.

Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.