Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the APM Project Fundamentals Qualification APM-PFQ Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam APM-PFQ Premium Access

View all detail and faqs for the APM-PFQ exam


727 Students Passed

93% Average Score

91% Same Questions
Viewing page 10 out of 13 pages
Viewing questions 91-100 out of questions
Questions # 91:

Which one of the following is a responsibility of the project steering group/board?

Options:

A.

To identify potential problems for the project team to solve.

B.

To provide strategic direction and guidance to the sponsor.

C.

To manage the project team in all daily activities.

D.

To receive and consider daily reports from team members.

Questions # 92:

Scheduling can best be defined as the process used to determine:

Options:

A.

overall project duration.

B.

project cost.

C.

the project management plan.

D.

sub-contractor's responsibilities

Questions # 93:

What aspect of the project will have greatest influence on the estimating method being used?

Options:

A.

The point in the life cycle where the estimate is being carried out.

B.

The overall budgeted value of the project being estimated.

C.

Whether the project is likely to proceed or not.

D.

The amount of acceptable estimating tolerance that exists.

Questions # 94:

Comparative estimating uses:

Options:

A.

current data from similar projects.

B.

historic data from all projects.

C.

historic data from similar projects.

D.

current data from all projects.

Questions # 95:

Which of the following are the major stakeholders of the project management plan?

1) Project sponsor

2) General public

3) Project team

4) Project manager

Options:

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4

Questions # 96:

Which of the following are challenges for a project manager developing and leading a project team?

1) Issues and incompatibility amongst team members

2) Getting the right skills and attributes amongst team members

3) Co-location of team members in the same geographic area

4) Lack of accountability of team members

Options:

A.

1, 2 & 3

B.

1, 2 & 4

C.

1, 3 & 4

D.

2, 3 & 4

Questions # 97:

Which of these is a correct definition of an Estimate?

Options:

A.

The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work

B.

An educated guess that improves over time

C.

A forecast of the probable time or cost of completing work

D.

An estimate is an approximation of project time and cost targets that forms the basis of the contract

Questions # 98:

Which one of the following best describes A. programme?

Options:

A.

A group of projects collected together that have a common purpose.

B.

A group of projects collected together for management convenience.

C.

A group of projects collected together because of their use of common resources.

D.

A group of projects collected together because of their relationship to business-as-usual.

Questions # 99:

Which of the following is a purpose of issue management?

Options:

A.

To stop issues occurring within the project.

B.

To address and resolve the issues that occur.

C.

To address and resolve uncertainty.

D.

To reschedule activities to reduce costs

Questions # 100:

Portfolio management involves:

1) selection

2) control

3) prioritisation

4) transition

Options:

A.

1, 2 and 3

B.

1, 2 and 4

C.

2, 3 and 4

D.

1, 3 and 4

Viewing page 10 out of 13 pages
Viewing questions 91-100 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.