Questions # 61:

What is the main objective of an audit?

Options:

A.

Provide assurance to the project sponsor that the project is going to finish

on time and within budget.

B.

Provide feedback to the project manager with regard to their performance in managing the project.

C.

Provide assurance to the sponsor that the project is being managed using the agreed governance and process.

D.

Provide a report of the current status of the project regarding cost and schedule performance.

Questions # 62:

Once a change has been requested what is the next step in the change control process?

Options:

A.

Evaluate the change.

B.

Advise the sponsor.

C.

Update the change log.

D.

Update the project plan.

Questions # 63:

Which technique could be used by a project manager when resources are limited?

Options:

A.

Resource aggregation.

B.

Resource estimation.

C.

Resource levelling.

D.

Resource expansion

Questions # 64:

What is the main purpose of iterations in an iterative life cycle?

Options:

A.

To reassure stakeholders that the project will deliver as expected

B.

To progressively elaborate and improve understanding based on client interaction.

C.

To allow time for a thorough project management plan to be developed.

D.

To ensure that the project manager appointed understands exactly what is required

Questions # 65:

How is it determined whether a deliverable conforms to its requirements and configuration information?

Options:

A.

A configuration management plan is produced

B.

A configuration identification reference is allocated to the deliverable.

C.

A configuration verification audit is performed.

D.

A status accounting report is produced.

Questions # 66:

Which of the following is an activity in a typical change control process?

Options:

A.

Recommendation.

B.

Justification.

C.

Planning.

D.

Continuous improvement

Questions # 67:

The definition of benefits management includes which key activities?

Options:

A.

Planning, analysis and integration of project benefits.

B.

Justification, validation and acceptance of project benefits.

C.

Identification, tracking and realisation of project benefits.

D.

Realisation, acceptance and integration of project benefits

Questions # 68:

What is the main aim of the communication plan?

Options:

A.

To increase the chances of achieving effective engagement.

B.

To comply with the structure of the project management plan.

C.

To identify the skills necessary to deliver a project.

D.

To increase the likelihood of benefits realisation.

Questions # 69:

One aspect of quality planning is to:

Options:

A.

plan the audit of a project to provide assurance to the project board.

B.

provide confidence that a project will achieve its objectives in the required time frame.

C.

specify the acceptance criteria used to validate the outputs are fit for purpose.

D.

confirm routes for reporting to ensure effective communication

Questions # 70:

Which of the following are typical estimating methods? 1) Analytical 2) Budgeting 3) Analogous 4) Parametric

Options:

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4