Questions # 251:

Which illustrates the connection between work that needs to be done and its project team members?

Options:

A.

Work breakdown structure (WBS)

B.

Network diagrams

C.

Staffing management plan

D.

Responsibility assignment matrix (RAM)

Questions # 252:

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Questions # 253:

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Questions # 254:

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Questions # 255:

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

Options:

A.

Organizational standard processes

B.

Marketplace conditions

C.

Historical information

D.

Templates

Questions # 256:

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

Options:

A.

Budget plan

B.

Resource plan

C.

Scope plan

D.

Strategic plan

Questions # 257:

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Questions # 258:

A procurement management plan is a subsidiary of which other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Questions # 259:

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Questions # 260:

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Questions # 261:

An input of the Plan Procurement Management process is:

Options:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Questions # 262:

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Questions # 263:

Which of the following tools or techniques is used for Estimate Activity Durations?

Options:

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

Questions # 264:

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Questions # 265:

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Questions # 266:

Which of the following is a tool and technique for Estimate Activity Durations?

Options:

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

Questions # 267:

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Questions # 268:

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Questions # 269:

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Questions # 270:

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Questions # 271:

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Questions # 272:

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Questions # 273:

The product scope description is used to:

Options:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Questions # 274:

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Questions # 275:

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Questions # 276:

An output of the Develop Project Team process is:

Options:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

Questions # 277:

An output of Control Schedule is:

Options:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Questions # 278:

The scope management plan is a subsidiary of which project document?

Options:

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Questions # 279:

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.

B.

It requires recipients to access communication content at their own discretion.

C.

It is the most efficient way to ensure a common understanding among all participants.

D.

It is primarily used when the volume of information to be transferred is minimal.

Questions # 280:

An input of the Control Schedule process is the:

Options:

A.

resource calendar.

B.

activity list.

C.

risk management plan.

D.

organizational process assets.

Questions # 281:

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Questions # 282:

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Questions # 283:

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Questions # 284:

Taking out insurance in relation to risk management is called what?

Options:

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Questions # 285:

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Questions # 286:

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Questions # 287:

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

Questions # 288:

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Questions # 289:

The diagram below is an example of a:

Question # 289

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Questions # 290:

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Questions # 291:

The probability and impact matrix is primarily used to:

Options:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Questions # 292:

One of the objectives of a quality audit is to:

Options:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Questions # 293:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Questions # 294:

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Questions # 295:

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Questions # 296:

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Questions # 297:

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Questions # 298:

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Questions # 299:

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

Options:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Questions # 300:

Which risk response strategy is common for both positive and negative risks?

Options:

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Viewing page 6 out of 8 pages
Viewing questions 251-300 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.