Questions # 101:

In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

Options:

A.

Involvement is needed only during project initiation.

B.

Minimal involvement of stakeholders is sufficient.

C.

They should be continuously engaged.

D.

They should be involved only during phase or deliverable reviews.

Questions # 102:

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Questions # 103:

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Questions # 104:

The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?

Options:

A.

Team values, team agreements, and conflict resolution process

B.

Conflict resolution process, communication guidelines, and meeting schedules

C.

Team roles and responsibilities, team management, and training plan

D.

Resource requirements, resource assignments, and team performance assessments

Questions # 105:

Which conflict resolution technique produces the most lasting results?

Options:

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Questions # 106:

To which knowledge area does the Collect Requirements process belong?

Options:

A.

Quality Management

B.

Scope Management

C.

Cost Management

D.

Integration Management

Questions # 107:

Which of the following is an example of facit knowledge?

Options:

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Questions # 108:

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

Options:

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

Questions # 109:

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

Options:

A.

Tornado diagrams and influence diagrams

B.

Detectability bubble charts and probability and impact matrix

C.

Hierarchical charts and burndown charts

D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts

Questions # 110:

Which of the following are components of the technical project management skill?

Options:

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Questions # 111:

A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?

Options:

A.

Collective decision making

B.

Multicriteria decision analysis

C.

Mind mapping

D.

Affinity diagram

Questions # 112:

It you established a contingency reserve including time, money, and resources, how are you handling risk?

Options:

A.

Accepting

B.

Transferring

C.

Avoiding

D.

Mitigating

Questions # 113:

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Questions # 114:

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

Options:

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

Questions # 115:

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Questions # 116:

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Questions # 117:

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Questions # 118:

When closing a project or phase, part of the process may require the use of which type of analysis?

Options:

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Questions # 119:

The following chart contains information about the tasks in a project.

Question # 119

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Questions # 120:

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Questions # 121:

An issue log is an input to which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

Questions # 122:

A tool and technique used in the Develop Project Charter process is:

Options:

A.

change control tools

B.

expert judgment

C.

meetings

D.

analytical techniques

Questions # 123:

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Questions # 124:

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Questions # 125:

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

Questions # 126:

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Questions # 127:

The following is a network diagram for a project.

Question # 127

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Questions # 128:

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Questions # 129:

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Questions # 130:

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Questions # 131:

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Questions # 132:

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Questions # 133:

The following is a network diagram for a project.

Question # 133

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Questions # 134:

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Questions # 135:

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Questions # 136:

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Questions # 137:

An example of a group decision-making technique is:

Options:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Questions # 138:

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Questions # 139:

A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

Options:

A.

cultural differences of team members

B.

possibility of communication misunderstandings

C.

costs associated with travel

D.

costs associated with technology

Questions # 140:

An input to the Control Quality process is:

Options:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Questions # 141:

Which stakeholder approves a project's result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Questions # 142:

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Questions # 143:

The chart below is an example of a:

Question # 143

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Questions # 144:

A graphic display of project team members and their reporting relationships is known as a:

Options:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Questions # 145:

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Questions # 146:

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

Options:

A.

management

B.

response

C.

tolerance

D.

appetite

Questions # 147:

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Questions # 148:

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Options:

A.

work package

B.

deliverable

C.

milestone

D.

activity

Questions # 149:

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Questions # 150:

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline