Questions # 151:

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Questions # 152:

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Questions # 153:

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Questions # 154:

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Questions # 155:

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Questions # 156:

In project management, a temporary project can be:

Options:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Questions # 157:

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Questions # 158:

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Questions # 159:

Which project risk listed in the table below is most likely to occur?

Question # 159

Options:

A.

1

B.

2

C.

3

D.

4

Questions # 160:

In complex projects/ initiating processes should be completed:

Options:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Questions # 161:

Which output is the approved version of the time-phased project budget?

Options:

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Questions # 162:

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Questions # 163:

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Options:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Questions # 164:

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

Options:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

Questions # 165:

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram