Questions # 76:

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.

B.

response,

C.

perception.

D.

impact.

Questions # 77:

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Questions # 78:

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Questions # 79:

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Questions # 80:

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Questions # 81:

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

Options:

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Questions # 82:

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Questions # 83:

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Questions # 84:

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Questions # 85:

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Questions # 86:

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Questions # 87:

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Questions # 88:

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

Questions # 89:

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Questions # 90:

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

Options:

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Viewing page 6 out of 15 pages
Viewing questions 76-90 out of questions