Questions # 16:

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Questions # 17:

When can pre-assignment of project team members occur?

Options:

A.

When the project uses capital expenditures

B.

When the required staff can be acquired from outside sources

C.

When the project would be ignored due to travel expenses

D.

When the project is the result of specific people being promised as part of a competitive proposal

Questions # 18:

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Questions # 19:

Cost baseline is an output of which of the following processes?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Estimate Activity Resources

Questions # 20:

Which Process Group typically consumes the bulk of a project's budget?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Questions # 21:

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Questions # 22:

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Questions # 23:

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Questions # 24:

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Questions # 25:

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Questions # 26:

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Options:

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

Questions # 27:

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7

B.

8

C.

14

D.

16

Questions # 28:

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Questions # 29:

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Questions # 30:

An input required in Define Scope is an organizational:

Options:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.