Viewing page 3 out of 15 pages
Viewing questions 31-45 out of questions
Questions # 31:

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Questions # 32:

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Questions # 33:

What type of reward can hurt team cohesiveness?

Options:

A.

Sole-sum

B.

Win-lose

C.

Lose-win

D.

Partial-sum

Questions # 34:

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Questions # 35:

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Questions # 36:

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Questions # 37:

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Questions # 38:

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Questions # 39:

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Questions # 40:

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Questions # 41:

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Questions # 42:

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Questions # 43:

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Questions # 44:

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Questions # 45:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Viewing page 3 out of 15 pages
Viewing questions 31-45 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.