Questions # 196:

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Questions # 197:

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Questions # 198:

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Questions # 199:

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Questions # 200:

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Questions # 201:

The Monitoring and Controlling Process Group includes processes that:

Options:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Questions # 202:

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Questions # 203:

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Questions # 204:

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Questions # 205:

The ability to influence cost is greatest during which stages of the project?

Options:

A.

Early

B.

Middle

C.

Late

D.

Completion

Questions # 206:

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Questions # 207:

A project manager builds consensus and overcomes obstacles by employing which communication technique?

Options:

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Questions # 208:

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Questions # 209:

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Questions # 210:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.