Questions # 166:

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Questions # 167:

Which tools or techniques are used during the Close Project or Phase process?

Options:

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Questions # 168:

For a stakeholder with low interest and high power, the project manager should:

Options:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Questions # 169:

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Questions # 170:

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Questions # 171:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

Questions # 172:

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result

B.

Product

C.

Service

D.

Improvement

Questions # 173:

A regression line is used to estimate:

Options:

A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Questions # 174:

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Options:

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Questions # 175:

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Questions # 176:

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Questions # 177:

Which tool or technique is used in the Plan Scope Management process?

Options:

A.

Document analysis

B.

Observations

C.

Product analysis

D.

Expert judgment

Questions # 178:

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

Options:

A.

smooth/accommodate.

B.

force/direct,

C.

collaborate/problem solve,

D.

compromise/reconcile.

Questions # 179:

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Questions # 180:

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case