Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror
Exam PMP Premium Access
View all detail and faqs for the PMP exam
848 Students Passed
84% Average Score
98% Same Questions
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?
In the middle of an iteration, the product owner tells the agile team that the
government has updated legal requirements. This will result in some changes in the product
definition.
How should the project manager handle this situation?
A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.
What is the appropriate course of action for the project manager to pursue?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.
What should the project manager do?
A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.
What should the project manager do?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
A project manager was recently assigned to a new project that is about to start. The
organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?
A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline
What should the project manager do next?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?
During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.
What should the project manager do?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables
How should the project manager mitigate this risk without compromising the completion date?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.
What should the project manager do to engage the stakeholders?
A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.
What should the project lead have done initially to avoid this situation?
A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution
What should the project manager do?
During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.
How should the project manager ensure the product increments deliver the anticipated requirements?
A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.
What should the project manager do next?
During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.
What should the project manager do next?
Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.
What should the project manager do?
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications
What should the project manager do?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.

Chart, line chart
Description automatically generated
Chart, square
Description automatically generated