Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PMP Premium Access

View all detail and faqs for the PMP exam


848 Students Passed

84% Average Score

98% Same Questions
Viewing page 14 out of 14 pages
Viewing questions 651-700 out of questions
Questions # 651:

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

Options:

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

Questions # 652:

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

Options:

A.

Requirements traceability matrix

B.

Risk management plan

C.

Project scope statement

D.

Requirements management plan

Questions # 653:

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

Options:

A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

B.

Ask the construction manager to meet with the two team members to resolve the situation.

C.

Provide the construction manager with instructions on how to resolve the situation.

D.

Discuss the team members' concern with the construction manager and seek solutions.

Questions # 654:

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?

Options:

A.

Recurrent team meetings are planned to control the budget against future uncertainties.

B.

Probabilistic analysis was used to develop the budget to address future uncertainties.

C.

The budget was developed by using the lessons learned from previous project data.

D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Questions # 655:

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

Options:

A.

Use templates from an existing project.

B.

Ask the project management office (PMO) for guidance.

C.

Surveying peers to understand what templates they have used.

D.

Lead the project team in finding the best templates.

Questions # 656:

A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.

What should the project manager do next?

Options:

A.

Schedule a team-building workshop involving all teams to support better communication.

B.

Schedule a meeting and ask all teams to sort the issues and move ahead with full participation.

C.

Ask everyone to only invite team members in different parts of the world as necessary.

D.

Share the time-overlap schedule with the team to make meeting scheduling convenient.

Questions # 657:

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Questions # 658:

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project's daily standup meetings.

D.

Align with the other project manager's high-level project time lines.

Questions # 659:

In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.

What should the project manager do?

Options:

A.

Invite team members to volunteer for roles for which they feel qualified.

B.

Revoke the delegated responsibilities to keep the team members harmonious.

C.

Remind team members that administrative decisions are the project manager's duties.

D.

Explain the rationale for delegating responsibilities to team members.

Questions # 660:

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

Options:

A.

Define the project management plan.

B.

Estimate the resources needed for the activities.

C.

Consult subject matter experts (SMEs) to review the schedule.

D.

Estimate the cost of each activity.

Questions # 661:

A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the

system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the

year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?

Options:

A.

Reassure the sponsor by explaining the probability of this risk materializing is extremely low.

B.

Carry out tests to verify that the system does not fail again due to the high occurrence of events.

C.

Review the list of risks to verify that this issue was considered and execute the detailed action plan.

D.

Inform the sponsor about the issue and make a request for sufficient funds to be made available.

Questions # 662:

A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

Options:

A.

334 person/day

B.

285 person/day

C.

310 person/day

D.

315 person/day

Questions # 663:

A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.

What should the project lead do?

Options:

A.

Determine the minimum communications needed for the project, and adapt the communication plans as needed.

B.

Document only the plan for written communications, and send meeting invites for verbal communication sessions.

C.

Follow the project management office (PMO) guidelines for communications instead of generating a project communications management plan.

D.

Create a communications management plan informing all project team members and stakeholders who will receive what type of communication.

Questions # 664:

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?

Options:

A.

Determine potential threats regarding compliance with the regulations.

B.

Ask human resources (HR) to assign a compliance specialist to the team.

C.

Validate that the software is compliant with standards and regulations.

D.

Measure the extent to which the project complies with the regulations.

Questions # 665:

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.

Provide the team with the enterprise environmental factors (EEFs).

B.

Run a benchmark with similar sites to compare compliance constraints.

C.

Look into lessons learned documentation for similar projects.

D.

Hire a specialized engineer to support the design team.

Questions # 666:

A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.

How should the project manager mitigate this situation?

Options:

A.

Execute a retrospective meeting to solve the misalignment.

B.

Review the actions listed in the risk management plan.

C.

Review and update the organizational process assets (OPAs).

D.

Submit a change request to replace the product owner.

Questions # 667:

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Questions # 668:

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.

Involve all of the stakeholders in the escalation by setting up a conference call.

B.

Escalate to the other party's management and inform the steering committee.

C.

Reach out to peer managers for similar escalation situations and follow past experiences.

D.

Review the established project escalation process and take the appropriate action.

Questions # 669:

The CFO has stated in a conversation with a project team member that they do not believe the project will be a success due to the high cost of implementation.

What should the project manager do?

Options:

A.

Meet with the CFO one-on-one to fully understand their cost concerns.

B.

Ask the project team to look for opportunities to cut project costs.

C.

Carry out a benefit analysis to present at the next project team meeting.

D.

Meet with the CFO and team to remind them of the project's key success measures.

Questions # 670:

A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?

Options:

A.

Perform contract, financial, and administrative tasks.

B.

Finalize the in-progress administrative tasks.

C.

Evaluate contract and administrative tasks.

D.

Execute financial and administrative tasks.

Questions # 671:

An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.

What should the project manager do next?

Options:

A.

Have the kick-off meeting as scheduled and capture any new requirements raised in the meeting.

B.

Have a one-on-one interview with the new senior manager before the kick-off meeting.

C.

Ask the new senior manager to send any new requirements before the kick-off meeting.

D.

Ask the project sponsor to hold the kick-off meeting after the new senior manager has onboarded.

Questions # 672:

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Options:

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Questions # 673:

During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.

What should the project manager do?

Options:

A.

Review and update the project management plan to accommodate the delays.

B.

Speak with the project sponsors about changing the project management plan.

C.

Create a change request to increase the cost of resources.

D.

Delay the project until additional resources can be identified.

Questions # 674:

During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?

Options:

A.

Replace the team member with another available resource on the team.

B.

Discuss the situation with the team member's functional manager to see if the schedule can be adjusted.

C.

Check with the project management office (PMO) on the available resources to complete the activities.

D.

Encourage the team member to prioritize scheduled project activities.

Questions # 675:

Drag the items on left side to the matching term within the correct project approach on the right side.

Question # 675

Options:

Questions # 676:

The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.

What should the project manager do?

Options:

A.

Determine alternative solutions to provide improved stakeholder visibility and engagement.

B.

Invite the stakeholder to the demo session and request their feedback about which direction to follow.

C.

Prioritize all of the requirements that are critical to the stakeholder in the next planning session.

D.

Review the scope with the stakeholder, request their feedback, and create an action plan.

Questions # 677:

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

Options:

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

Questions # 678:

During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.

What should the project manager do next?

Options:

A.

Ask the vendor for revised timelines and cost needs.

B.

Review the acceptance criteria defined with the vendor.

C.

Communicate with the vendor for contract changes.

D.

Request cancellation of the contract with the vendor.

Questions # 679:

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

Options:

A.

Organize a training for the new team member on the processes the team is currently using.

B.

Speak with the new team member at the retrospective and discuss potential improvements.

C.

Formalize the new processes and implement the team member's proposed changes.

D.

Hold a team meeting on governance, operating policies, procedures, and practices.

Questions # 680:

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?

Options:

A.

Feedback from the project sponsor

B.

Agreed-upon key performance indicators (KPIs)

C.

Input from project stakeholders

D.

Competencies of team members

Questions # 681:

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?

Options:

A.

US$35,000

B.

US$20,000

C.

US$40,000

D.

US$30,000

Questions # 682:

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

Options:

A.

Distribute the release plan among the team members.

B.

Ask the team members to focus only on their assignments.

C.

Ask the product owner to clarify the project's vision with the team.

D.

Meet with the product owner to validate the backlog prioritization.

Questions # 683:

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.

What should the project manager do next?

Options:

A.

Discuss extending the mass production timeline by 3 months with the project sponsor.

B.

Meet with senior management to discuss the possibility of an extension to the project timeline.

C.

Engage a consultant to shorten the certification process to meet the schedule requirement.

D.

Assess and evaluate the certification process and understand the best and worst case scenarios.

Questions # 684:

A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.

Which approach should the project manager use in this situation?

Options:

A.

Hybrid approach

B.

Predictive approach

C.

Kanban approach

D.

Agile approach

Questions # 685:

A new employee has joined the management team and wants to get a quick overview of all the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?

Options:

A.

Review the information radiators for each project.

B.

Connect with each project's scrum master to assess progress.

C.

Meet with each project's development team separately.

D.

Attend the daily standup meetings for each project.

Questions # 686:

A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.

Match the following common terms with their explanations that evaluate the buffers or constraints.

Question # 686

Options:

Questions # 687:

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?

Options:

A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.

B.

Work with the team to understand what can motivate them to try and complete the project.

C.

Remind the team of their commitment with the client and the need to adapt to the client's needs.

D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.

Questions # 688:

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.

What should the project manager do?

Options:

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Inform the customer of the impact immediately and prepare for escalation.

D.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

Questions # 689:

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?

Options:

A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.

B.

Reject the review as the completed project timeline is set by the company's CEO and has already been approved.

C.

Agree to review the architect's new proposal to assess the impact on the timelines set by the CEO.

D.

Register an issue in the log regarding the timeline delay to the CEO's approved plans before agreeing to change the project scope.

Questions # 690:

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?

Options:

A.

Invite the new manager to the next daily scrum.

B.

Invite the new manager to the next sprint review.

C.

Invite the new manager to the next sprint planning.

D.

Invite the new manager to the next sprint retrospective.

Questions # 691:

A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.

What should the project manager have done to prevent this?

Options:

A.

Deployed to production after the first iteration

B.

Reviewed the compliance requirements with stakeholders

C.

Planned smaller iterations to review the results more often

D.

Implemented the authorization in the first iteration

Questions # 692:

A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.

What should the project manager do?

Options:

A.

Use the contingency budget to implement compression techniques to finish the current project phase early.

B.

Review the stakeholder engagement plan and determine the best course of action to take.

C.

Notify the outgoing sponsor that the project needs to be put on hold until the new sponsor is onboarded.

D.

Submit a change request to the change control board (CCB) to modify the end date of the current phase.

Questions # 693:

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.

Which two actions should the project manager leverage to ensure the team is meeting performance expectations?

(Choose two)

Options:

A.

Hold daily virtual meetings to review progress.

B.

Implement time-keeping software for team members.

C.

Task functional managers to drive accountability.

D.

Utilize a web-based kanban board.

E.

Require a monthly individual status report.

Questions # 694:

During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.

What should the project manager do first?

Options:

A.

Assign the work based on the skill sets of team members.

B.

Request feedback from stakeholders about the quality delivery.

C.

Assign the work in consultation with the functional manager.

D.

Discuss this with the team and review the quality process.

Questions # 695:

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Options:

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Questions # 696:

A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.

What should the project manager do?

Options:

A.

Meet with each team member to better understand the situation.

B.

Meet with the extroverted team member and ask them to be more sensitive to others.

C.

Address the situation in a team meeting and ask everyone to be more active.

D.

Observe the team dynamics closely and step in if a team member complains.

Questions # 697:

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?

Options:

A.

Include only the common requirements of each stakeholder group in the project goals.

B.

Include only the key requirements and keep the stakeholders informed about scope decisions.

C.

Analyze the interests and influence of stakeholders and evaluate their requirements.

D.

Add only the opinions of the team, because they know the objectives of the project.

Questions # 698:

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

Options:

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.

Questions # 699:

A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?

Options:

A.

Ask the team member to contact the learning and development team for additional help.

B.

Share the required documents with the team member.

C.

Arrange a required training session for the team member.

D.

Raise this issue in the next team meeting and ask the rest of the team to clarify.

Questions # 700:

A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.

What should the project manager do to avoid these situations?

Options:

A.

Review the risk management plan.

B.

Review the resource management plan.

C.

Review the communications management plan.

D.

Review the stakeholder engagement plan.

Viewing page 14 out of 14 pages
Viewing questions 651-700 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.