Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror
Exam PMP Premium Access
View all detail and faqs for the PMP exam
848 Students Passed
84% Average Score
98% Same Questions
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.
Which document should the project manager use to resolve this situation?
A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.
What should the project manager do to improve the situation?
At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.
How should the project manager reply?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.
What should the project manager do next?
An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.
What should the project manager have done first to avoid this situation?
A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.
What should the project manager do next?
In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.
What should the project manager do?
A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.
What is the estimate at completion (EAC)?
A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.
What should the project lead do?
A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?
During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.
What should the project manager do?
A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.
How should the project manager mitigate this situation?
A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.
What should the project manager suggest?
A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.
What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?
The CFO has stated in a conversation with a project team member that they do not believe the project will be a success due to the high cost of implementation.
What should the project manager do?
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.
What should the project manager do next?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.
What should the project manager do?
During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?
Drag the items on left side to the matching term within the correct project approach on the right side.
The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
A project manager is looking for ways to keep the budget on track throughout the project life cycle.
What should the project manager do to ensure that happens?
During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.
What should the project manager do next?
A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.
What action should the project manager take?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?
In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to
evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4
months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the
following resources:
* Two engineers (monthly salary of US$700 each)
* One project manager (monthly salary of US$1,600)
* Additional estimated monthly expenses of US$2,000
The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house
resources.
How much money will the project manager estimate the company can save?
A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.
How should the project manager address this situation?
A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.
What should the project manager do next?
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.
Which approach should the project manager use in this situation?
A new employee has joined the management team and wants to get a quick overview of all the agile team's projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?
A project team has developed the initial schedule using a network diagramming method and has arrived at the overall project duration. Upon examining the schedule, the project manager finds that there are several activities that may require buffers to mitigate or eliminate potential scheduling conflicts.
Match the following common terms with their explanations that evaluate the buffers or constraints.
A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.
What should the project manager do first?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.
What should the project manager do?
A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.
What should the project manager recommend?
A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.
What should the project manager do?
A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.
What should the project manager have done to prevent this?
A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.
What should the project manager do?
A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations?
(Choose two)
During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.
What should the project manager do first?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.
What should the project manager do?
A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?
A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.
What should the project manager do next?
A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.

