Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror
Exam PMP Premium Access
View all detail and faqs for the PMP exam
848 Students Passed
84% Average Score
98% Same Questions
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.
How can the project manager strategize the use of a hybrid approach to the organization?
A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.
What should the project manager do first?
A project manager was notified about a new regulatory requirement that could impact the project schedule.
What should the project manager do first?
Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.
What should the project manager do to prevent this from happening again?
A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
A project team consists of several consultants from an external vendor. These consultants often change from month to month.
What should the project manager do to communicate the organizational values?
A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.
What should the project manager do to address the issue?
An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.
What should the project manager do?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
During a project's stakeholder identification stage, team members are struggling to identify the level of influence for two stakeholders. One is considered important, while the second is not quite as important as the first one. For this project, stakeholder engagement is a critical activity.
What should the project manager do?
A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.
What should the project manager do next?
An ongoing project with company A is impacted by the recent acquisition of company B. This could affect the current suppliers for the ongoing project.
What should the project manager do next?
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.
What should the project manager do next?
An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?
A project manager works with a multifunctional team. During a review meeting, two team members disagree on the development approach.
What should the project manager do?
A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.
What should the project manager do?
A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.
What should the project manager do?
A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).
Which two steps should the project lead take to define the MVP? (Choose 2)
A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.
What should the project manager do?
A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.
What should the project manager do?
A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for
the project. The customer has informed the project manager to disregard the group as they are not in support of the project.
What should the project manager do next?
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.
During the iteration retrospective, the team realizes that the complexity of the work was underestimated.
What should the project manager do?
A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?
A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.
How should the project manager handle the situation?
A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?
A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.
What should the project lead do to obtain the needed resources?
A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?
A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?
A key stakeholder of a project wants to include additional work before completion.
What should the project manager do?
A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.
What should the project manager do?
A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.
What should the project manager do?
Project team member A has a conflict with project team member B. The project manager believes project team member A's behavior is unacceptable. However, project team member A believes their behavior is appropriate.
What should the project manager do?
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase, the business stakeholders were unable to understand the feature integration with the product and raised concerns.
What can the project manager do to demonstrate the feature integration?
An investment company is interested in unifying direction and control criteria in one of its principal projects. The project manager was advised to enforce the main framework of this initiative.
What should the project manager do first?
A project manager is leading a highly visible project with a critical time constraint. Frequent scope changes have been well-managed with change control, but there have been misunderstandings among project team members.
What should the project manager do?
A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.
What should the project manager do to ensure the project is completed on time with quality?
A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.
What should the project lead use for backlog refinement considering the sprints are 2 weeks long?
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner's preferred language; however, they are very skilled in the other language.
What should the project manager do?
A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.
What should the project manager do to select the most effective project framework?
Negotiations are underway to secure an agreement with a critical supplier for the project. The negotiation situation has become contentious as it is becoming apparent that both parties will not receive everything they want and that a compromise might be necessary to avoid project delays, cost overruns, and damage to reputations.
What should the project manager do to help ensure a successful outcome for the project?
A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.
What should the project manager do?
Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.
What should the project manager do?
A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.
What should the project manager do?
A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?
A project team is experiencing communication issues during project execution. The project manager realizes that the communications management plan needs to be reviewed.
Which are three fundamental actions the project manager should take? (Choose 3)
The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?
A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.