Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the PMI Project-Management-Professional PMP Questions and answers with ExamsMirror
Exam PMP Premium Access
View all detail and faqs for the PMP exam
848 Students Passed
84% Average Score
98% Same Questions
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies
What should the project manager do?
During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.
What should the project manager do next in this situation?
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1.500 rpm (rate-per-minute) -> warns of max rate allowed
1.400pm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago
What should the project manager do to analyze the involved stakeholders?
A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required
How should the project manager assist the product owner?
A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.
What should the project manager do?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level
What should the project manager do next with this opportunity?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects
What should the project manager do to ensure the project scope is completely defined?
The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible
What three actions should the project manager take to address this situation? (Choose three)
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork
What should the project manager do to improve morale?
The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?
The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?
An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project
What should the project manager do?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team
What should the project manager do?
A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task
What should the project manager do to obtain the information required by the developer?
After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings
What is one of the key activities that the project manager should undertake to ensure company success?
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again
What should the project lead do next?
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting
What should the project manager do?
Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members
What should the project manager do?
After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features
What should the project manager do to avoid this in the future?
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.
What should the project lead do in this situation?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?
A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion
What two actions should the project manager take? (Choose two)
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?
During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?
A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.


