Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70

Pass the AACE International Professional Level Certifications PSP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PSP Premium Access

View all detail and faqs for the PSP exam


506 Students Passed

92% Average Score

94% Same Questions
Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions
Questions # 1:

Budgeted cost of work scheduled is _______________________.

Options:

A.

The value of the completed work expressed in terms of the budget assigned to that work

B.

The total authorized budget for accomplishing the project scope

C.

The expected total cost of an activity, group of activities or the project

D.

The sum of all budgets for work scheduled to be accomplished within a given time period

Questions # 2:

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Questions # 3:

Which of the following phases does NOT describe the commonly accepted construction life cycle?

Options:

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Questions # 4:

What does the narrow band at "Y" represent?

Question # 4

Options:

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Questions # 5:

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Question # 5

Options:

A.

19 months.

B.

20 months.

C.

22 months.

D.

21 months.

Questions # 6:

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Options:

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

Questions # 7:

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

Options:

A.

Finish-no-earlier constraint on the first activity

B.

Finish-no-earlier constraint on the last activity

C.

Finish-no-later constraint on the last activity

D.

Start-no-later constraint on the first activity

Questions # 8:

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Question # 8

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Questions # 9:

Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

Question # 9

Options:

A.

06-11-02.

B.

06-04-02.

C.

06-18-02.

D.

06-05-02.

Questions # 10:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

Question # 10

Options:

A.

Delay product release by 5 days.

B.

Expedite packaging by 5 days.

C.

Expedite printing by 5 days.

D.

Delay manufacturing by 5 days.

Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.