Questions # 11:

Why does activity 1001 have two successor activities?

Question # 11

Options:

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Questions # 12:

What is the free float for Activity F?

Question # 12

Options:

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Questions # 13:

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Questions # 14:

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

Options:

A.

Is a milestone.

B.

It is on the critical path.

C.

Was completed in the past.

D.

Has yet to be completed.

Questions # 15:

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Options:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Questions # 16:

How could the structural steel drawing delay have been prevented?

Options:

A.

Add a time buffer at the end of structural steel activities.

B.

Allow adequate time for review and resubmittal in the baseline schedule.

C.

Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

D.

Switch to post-tensioned concrete construction.

Questions # 17:

What owner action could have mitigated the late completion of the project?

Options:

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Questions # 18:

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Question # 18

Options:

A.

02-19-04

B.

03-21-04

C.

03-11-04

D.

03-20-04

Questions # 19:

What project cost elements would NOT normally be reflected in the Activity 1000?

Options:

A.

Home office expenses

B.

CPM processing and updating

C.

Materials used in the construction

D.

Job site quality control

Questions # 20:

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.

B.

Replace the relationship from 'B’ to 'C’ with SSO

C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort