Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the AACE International Professional Level Certifications PSP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PSP Premium Access

View all detail and faqs for the PSP exam


834 Students Passed

88% Average Score

94% Same Questions
Viewing page 4 out of 7 pages
Viewing questions 31-40 out of questions
Questions # 31:

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

Question # 31

Options:

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Questions # 32:

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

Questions # 33:

What is accurate about Activity 7001 in the precedence diagram?

Options:

A.

The successor FF lag from 7001 to 11001 is not shown

B.

The LF is correct

C.

The TF is not calculated correctly

D.

The LF is not correct

Questions # 34:

At the end of month one, did the delay to the parking structure foundation delay the project?

Options:

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

Questions # 35:

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

Options:

A.

/

B.

Bell curve

C.

S

D.

_

Questions # 36:

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

Options:

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

Questions # 37:

Background

Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.

It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.

You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.

With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.

In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.

1. Pull the project team together and ensure everyone understands which activities are on the critical path. Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.

2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.

3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.

4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.

Assignment

Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:

a. the current problem and potential impact(s);

b. each course of action, stating advantages and disadvantages as appropriate;

c. your recommendations, properly supported.

Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).

While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.

Take time to read the problem and consider what you want Evan to say. Good luck!

Options:

Questions # 38:

Which of the following statements is true?

Options:

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor

B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor

C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner

D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor

Questions # 39:

What does the heavy, vertical line at "X" represent?

Question # 39

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Questions # 40:

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

Options:

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Viewing page 4 out of 7 pages
Viewing questions 31-40 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.