Questions # 61:

Project Life Cycle Phases do NOT include the following item:

Options:

A.

procurement

B.

budgeting

C.

design

D.

start-up

Questions # 62:

Is activity 7001 pictured correctly in the precedence diagram?

Question # 62

Options:

A.

No, the total float is not shown correctly.

B.

Yes, except the early finish date is not shown.

C.

No, the start-to-start and finish-to-finish relationships are backwards.

D.

Yes, the duration is 48 days.

Questions # 63:

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Question # 63

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Questions # 64:

Which of the following is NOT input data to the construction planning process?

Options:

A.

Input from the owner

B.

The contract

C.

Bonding capacity of subcontractors

D.

Input from the contractor

Questions # 65:

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

Question # 65

Options:

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Questions # 66:

Using the normal schedule, what is the owner's total cost of the project?

Options:

A.

S13.990.600

B.

S12.990.000

C.

S13.102.900

D.

S12.953.600

Questions # 67:

What is the cycle time?

Question # 67

Options:

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Questions # 68:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Questions # 69:

Constructability is NOT intended to:

Options:

A.

optimize engineering and procurement

B.

correct deficiencies in the project design

C.

balance project and environment goals

D.

integrate construction knowledge into the design

Questions # 70:

What problems can a soils engineer deal with on a project?

Options:

A.

Survey error.

B.

Hidden subsurface conditions.

C.

Archeological findings.

D.

Toxic soils.