In a "crashed" schedule, which is a chain of activities that precede activity 2004?

What is a critical path method schedule?
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
What is the result of a forward pass calculation?
During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

Which of the following will always describe the critical path? The path with
Due to the delayed completion of Product Testing, the Release for Manufacture milestone was delayed by 5 workdays which thus delayed starting the Draft Product Manual activity. If the Print Product Manual activity is also delayed by 10 workdays, what is the delay to completing the Product Available milestone?
Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?