Questions # 51:

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Question # 51

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Questions # 52:

What is a critical path method schedule?

Options:

A.

List of work to be accomplished by responsible party and when it is to be accomplished

B.

The timeline of the riskiest work

C.

A graphical means of showing the important work

D.

A network diagram of logically interconnected activities

Questions # 53:

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

Options:

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Questions # 54:

What is the result of a forward pass calculation?

Options:

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Questions # 55:

During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?

Options:

A.

The bid does not reflect details of planning and scheduling

B.

The bid should reflect the level of planning and scheduling noted on similar projects with this client

C.

The bid should reflect the project plan incorporating all planning and scheduling elements

D.

The bid should incorporate input from the manager responsible for planning and scheduling if the bid is successful

Questions # 56:

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

Question # 56

Options:

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Questions # 57:

Which of the following will always describe the critical path? The path with

Options:

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.

Questions # 58:

Due to the delayed completion of Product Testing, the Release for Manufacture milestone was delayed by 5 workdays which thus delayed starting the Draft Product Manual activity. If the Print Product Manual activity is also delayed by 10 workdays, what is the delay to completing the Product Available milestone?

Options:

A.

15 days

B.

0 days

C.

10 days

D.

5 days

Questions # 59:

Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?

Options:

A.

The cost variance

B.

The profit or loss for the project

C.

The variance at completion

D.

The schedule variance

Questions # 60:

Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

Question # 60

Options:

A.

11 Mar 2024

B.

21 Mar 2024

C.

19 Feb 2024

D.

20 Mar 2024

Viewing page 6 out of 7 pages
Viewing questions 51-60 out of questions