Questions # 41:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days

B.

Delay Release for Manufacture by 5 days

C.

Delay Manufacture Product by 5 days

D.

Expedite Package Product by 5 days

Questions # 42:

What day would Activity C complete if the duration of Activity A was reduced by five days?

Options:

A.

35

B.

30

C.

45

D.

40

Questions # 43:

Using the normal schedule, what is the early finish date and total float of Activity 10002?

Options:

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Questions # 44:

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Questions # 45:

What day would Activity C complete if the duration of Activity B was reduced to zero?

Options:

A.

50

B.

20

C.

30

D.

40

Questions # 46:

An early start constraint dictates

Options:

A.

An activity's remaining duration.

B.

The planned start of a successor activity

C.

The planned start of an activity.

D.

The actual start of an activity.

Questions # 47:

What is the actual duration as of the status date or data date of Activity B?

Question # 47

Options:

A.

7.

B.

3.

C.

0.

D.

4.

Questions # 48:

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

Options:

A.

263 CY

B.

368 CM

C.

201 CY

D.

306 CY

Questions # 49:

Activity C is a

Options:

A.

Contentious activity.

B.

Continuous activity.

C.

1-day activity.

D.

Milestone.

Questions # 50:

Determine the correct formula and date for the late start for the Activity 11001:

Question # 50

Options:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Viewing page 5 out of 7 pages
Viewing questions 41-50 out of questions