Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the AACE International Professional Level Certifications PSP Questions and answers with ExamsMirror
Exam PSP Premium Access
View all detail and faqs for the PSP exam
834 Students Passed
88% Average Score
94% Same Questions
When resource leveling craft labor for a critical path schedule, the scheduler
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
What is a key first step in developing a critical path method schedule?
Activity C is a
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.