Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the AACE International Professional Level Certifications PSP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PSP Premium Access

View all detail and faqs for the PSP exam


834 Students Passed

88% Average Score

94% Same Questions
Viewing page 3 out of 7 pages
Viewing questions 21-30 out of questions
Questions # 21:

When resource leveling craft labor for a critical path schedule, the scheduler

Options:

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Questions # 22:

In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

Question # 22

Options:

A.

2003 and 7001.

B.

2004.

C.

4001, 5001 and 6001.

D.

4001 and 5001.

Questions # 23:

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

Options:

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

Questions # 24:

What is a key first step in developing a critical path method schedule?

Options:

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

Questions # 25:

Activity C is a

Options:

A.

Contentious activity.

B.

Continuous activity.

C.

1-day activity.

D.

Milestone.

Questions # 26:

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

Options:

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Questions # 27:

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

Question # 27

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts

Questions # 28:

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

Question # 28

Options:

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Questions # 29:

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

Question # 29

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Question # 29

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Questions # 30:

The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

Options:

A.

Budget at completion (BAC)

B.

Budgeted cost of work performed (BCWP)

C.

Estimate to complete (ETC)

D.

Estimate at completion (EAC)

Viewing page 3 out of 7 pages
Viewing questions 21-30 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.