Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PMI Project-Management-Professional PMI-001 Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PMI-001 Premium Access

View all detail and faqs for the PMI-001 exam


734 Students Passed

87% Average Score

90% Same Questions
Viewing page 2 out of 14 pages
Viewing questions 21-40 out of questions
Questions # 21:

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Questions # 22:

An output of the Perform Integrated Change Control process is:

Options:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

Questions # 23:

Which tool or technique is used in the Estimate Costs process?

Options:

A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

Questions # 24:

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Questions # 25:

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Cost baseline

B.

Cost forecasting

C.

Cost variance

D.

Cost budgeting

Questions # 26:

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Questions # 27:

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Questions # 28:

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Questions # 29:

Projects are authorized by which of the following individuals?

Options:

A.

Project managers

B.

Stakeholders

C.

Functional managers

D.

Sponsors

Questions # 30:

Which of the following are outputs of the Monitor and Control Project Work process?

Options:

A.

Requested changes, forecasts, recommended corrective actions

B.

Forecasts, resources plan, bottom up estimating

C.

Recommended corrective actions, cost baseline, forecasts

D.

Requested changes, recommended corrective actions, project constraints

Questions # 31:

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

Options:

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

Questions # 32:

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Questions # 33:

How is quality control performed?

Options:

A.

By identifying quality standards that are relevant to the project and determining how to satisfy them

B.

By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed

C.

By ensuring that the entire project team has been adequately trained in quality assurance processes

D.

By applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards

Questions # 34:

The chart below is an example of a:

Question # 34

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Questions # 35:

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Questions # 36:

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Questions # 37:

An output of the Plan Quality Management process is:

Options:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Questions # 38:

The following chart contains information about the tasks in a project.

Question # 38

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Questions # 39:

An input to the Control Quality process is:

Options:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Questions # 40:

What is an objective of the Developing Project Team Process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers become more involved.

Viewing page 2 out of 14 pages
Viewing questions 21-40 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.