Questions # 81:

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Questions # 82:

Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

Options:

A.

Define Activities

B.

Direct and Manage Project Work

C.

Develop Project Management Plan

D.

Develop Project Charter

Questions # 83:

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Questions # 84:

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Questions # 85:

The lowest level normally depicted in a work breakdown structure (WBS) is called a/an:

Options:

A.

work package

B.

deliverable

C.

milestone

D.

activity

Questions # 86:

What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational Breakdown Structure (OBS)

B.

Work Performance Information

C.

Work Package

D.

Work Breakdown Structure (WBS)

Questions # 87:

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Questions # 88:

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

Options:

A.

Interrelationship digraphs

B.

Tree diagram

C.

Affinity diagram

D.

Network diagram

Questions # 89:

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Questions # 90:

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Questions # 91:

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Questions # 92:

Which of the following is a group decision-making technique?

Options:

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Questions # 93:

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Questions # 94:

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

Questions # 95:

Which Manage Communications tool or technique focuses on identifying and managing barriers?

Options:

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Questions # 96:

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

Options:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

Questions # 97:

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Questions # 98:

A contract management plan is a subsidiary of what other type of plan?

Options:

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Questions # 99:

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Questions # 100:

Requirements documentation will typically contain at least:

Options:

A.

Stakeholder requirements, staffing requirements, and transition requirements.

B.

Business requirements, the stakeholder register, and functional requirements.

C.

Stakeholder impact, budget requirements, and communications requirements.

D.

Business objectives, stakeholder impact, and functional requirements.

Viewing page 5 out of 14 pages
Viewing questions 81-100 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.