Questions # 91:

Final product transition is an output of which process?

Options:

A.

Direct and Manage Project Execution

B.

Close Project or Phase

C.

Perform Integrated Change Control

D.

Monitor and Control Project Work

Questions # 92:

A computer tape which contains historical project information is called ____ tape.

Options:

A.

Database

B.

Archive.

C.

Lessons learned.

D.

Baseline.

E.

Life cycle summary.

Questions # 93:

Which of the following is a tool and technique to develop the schedule?

Options:

A.

What-if scenario analysis

B.

Benchmarking

C.

Variance analysis

D.

SWOT analysis

Questions # 94:

During the initial stages of the project, what do activity attributes include?

Options:

A.

Activity name, dependencies, assumptions

B.

Activity ID, WBS ID, activity name

C.

Activity ID, assumptions, constraints

D.

Activity name, WBS ID, activity description

Questions # 95:

Life seems to be going very well for your close friend, a fellow PMP. She has taken a trip to France, bought a new car, and stocked her wine cellar with a half dozen expensive bottles of wine, all within the last six months. After a few cocktails one evening, she tells you her secret. The vendor she's working with on the $4 billion project she's managing has given her all of these items as gifts.

Which of the following should you do? (Choose the best answer.)

Options:

A.

You tell your friend these gifts probably aren't appropriate and leave it at that.

B.

Your friend doesn't see a problem with accepting these gifts at all. You know this is a conflict of interest situation and should be reported as a PMP Code of Professional Conduct violation.

C.

You and your friend have a long conversation about the gifts, and she decides to return them (with the exception of the trip) and not accept any more gifts in the future.

D.

You're happy for your friend and say nothing.

Questions # 96:

Which type of control tool identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram

B.

Control Charts

C.

Pareto Chart

D.

Histogram

Questions # 97:

Which type of tool would be used for the quality planning activity?

Options:

A.

Schedule Analysis

B.

Checklist Analysis

C.

Assumption Analysis

D.

Cost-Benefit Analysis

Questions # 98:

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope.

Which of the following statements is true?

Options:

A.

Performance measurement baselines might be affected by scope changes.

B.

Project scope change uses workarounds to correct unexpected problems with scope change.

C.

Project scope change uses inspection to determine whether change has occurred.

D.

Project scope changes do not require CCB approval.

Questions # 99:

Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your office works different hours than all the other offices. Additionally, not all of the resources in your building are available at the same times during the day. Three of the 12 team members work swing shift hours. You use tools like web conferencing and email to distribute information to the team.

Which of the following is true?

Options:

A.

This question describes resource availability from the Develop Project Team process and information distribution methods from the Information Distribution process.

B.

This question describes the staffing management plan from the Acquire Project Team process and communication skills from the Information Distribution process.

C.

This question describes project staff assignments from the Develop Project Team process and communication skills from the Information Distribution process.

D.

This question describes virtual teams from the Acquire Project Team process and information distribution methods from the Information Distribution process.

Questions # 100:

Which of the following does NOT assess the value a project brings to an organization?

Options:

A.

Benefit cost analysis

B.

Net present value

C.

Value analysis

D.

Needs assessment

Questions # 101:

You are a project manager of ABC organization. You are estimating the project in initiation phase.

What level of accuracy you can expect?

Options:

A.

-75 percent to +75 percent

B.

-25 percent to +25 percent

C.

-50 percent to +50 percent

D.

-50 percent to +100 percent

Questions # 102:

Advantages of the functional (hierarchical) form of organization include _____ and creation of technical competence.

Options:

A.

Single voice to customers

B.

High information processing capability

C.

Ease of horizontal coordination

D.

Clearly defined authority

Questions # 103:

You are negotiating with a seller. Time is of the essence but you have a limited budget, and the seller knows this.

What is your BEST negotiating strategy under these circumstances?

Options:

A.

Focus the negotiation on seller's profit margin in order to decrease the project cost.

B.

Negotiate to get the work done even sooner than necessary in order to add a reserve.

C.

Negotiate identified risks.

D.

Arrange to reschedule the negotiation until you can acquire information of which the seller is not aware.

Questions # 104:

Giving a part of project work to a contractor is an example of:

Options:

A.

risk assumption

B.

risk assignment

C.

risk delegation

D.

risk deflection

E.

risk mitigation

Questions # 105:

Which of the following inputs is required for the WBS creation?

Options:

A.

Project Quality Plan

B.

Project Schedule Network

C.

Project Management Software

D.

Project Scope Management Plan