Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the BCS Project & programme management and consultancy certifications ISEB-PM1 Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam ISEB-PM1 Premium Access

View all detail and faqs for the ISEB-PM1 exam


658 Students Passed

93% Average Score

91% Same Questions
Viewing page 9 out of 13 pages
Viewing questions 121-135 out of questions
Questions # 121:

You are working with XYZ organization. Your senior manager imposed new delivery date which is earlier than mentioned project deliverables date in scope statement.

To whom you are most accountable?

Options:

A.

customer

B.

team member

C.

sponsor

D.

senior manager

Questions # 122:

All the techniques described below can be used to keep a meeting focused except:

Options:

A.

Rephrase unclear ideas presented by group members

B.

Encourage pursuit of interesting new ideas

C.

Summarize discussion periodically

D.

Recall agenda items/purpose of meeting

E.

All are acceptable techniques

Questions # 123:

In which process might you use risk reassessment as a tool and technique?

Options:

A.

Qualitative risk analysis

B.

Risk monitoring and control

C.

Monitor and control project work

D.

Risk response planning

Questions # 124:

Which of the following would be the MOST appropriate thing to do during the planning process group?

Options:

A.

Update corporate processes and procedures based on lessons learned.

B.

Evaluate the effectiveness of risk responses.

C.

Recommend changes and defect repair.

D.

Work with the customer to determine acceptance criteria.

Questions # 125:

What should be covered in an implementation when the change is approved?

Options:

A.

Functional requirement

B.

Status report

C.

Customer need

D.

Defect repair

Questions # 126:

Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

Options:

A.

Risk response planning

B.

Risk monitoring and control

C.

Performance reporting

D.

Manage stakeholders

Questions # 127:

Which is the document that presents a hierarchical project organization?

Options:

A.

WBS

B.

CPI

C.

OBS

D.

BOM

Questions # 128:

Which of the following lists contain processes that are included within Project Procurement Management?

Options:

A.

Plan purchases and acquisitions, plan contracting, request seller responses, select sellers

B.

Plan purchases and acquisitions, request seller responses, select sellers, schedule control

C.

Plan purchases and acquisitions, acquire project team, request seller responses, select sellers

D.

Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Questions # 129:

What cost control technique is used to compare actual project performance to planned or expected performance?

Options:

A.

Cost aggregation

B.

Trend analysis

C.

Forecasting

D.

Variance analysis

Questions # 130:

In which type of organization does a project manager have a moderate-to-high resource availability?

Options:

A.

Functional

B.

Weak

C.

Balanced

D.

Strong

Questions # 131:

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?

Options:

A.

Under budget and behind schedule

B.

Over budget and ahead of schedule

C.

Under budget and ahead of schedule

D.

Over budget and behind schedule

Questions # 132:

What is one of the MAJOR outputs of activity sequencing?

Options:

A.

Responsibility assignment matrix

B.

Work breakdown structure update

C.

Project network diagram

D.

Mandatory dependencies list

Questions # 133:

Providing forecasts to update current cost and schedule information is a part of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Monitor and Control Risks

D.

Monitor and Control Project Work

Questions # 134:

Earned value measurement is an example of:

Options:

A.

Performance reporting.

B.

Planning control.

C.

Ishikawa diagrams.

D.

Integrating the project components into a whole.

Questions # 135:

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced