Questions # 61:

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Questions # 62:

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

Options:

A.

Performance organizations

B.

Schedule baselines

C.

Performance measurements

D.

Change requests

Questions # 63:

Negotiated Settlements are an example of a technique used in which Project Procurement Management Process?

Options:

A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Questions # 64:

Manage Project Team belongs to which knowledge area?

Options:

A.

Project Integration Management

B.

Project Time Management

C.

Project Procurement Management

D.

Project Human Resource Management

Questions # 65:

What are the identified risks for doing excessive decomposition in a WBS?

Options:

A.

Insufficient project funding and disqualification of sellers

B.

Insufficient project funding and ineffective use of resources

C.

Disqualification of sellers and non-productive management efforts

D.

Non-productive management effort and inefficient use of resources

Questions # 66:

What causes replanning of the project scope?

Options:

A.

Requested changes

B.

Project scope statement changes

C.

Variance analysis

D.

Approved change requests

Questions # 67:

Which tool or technique measures performance of the project as it moves from project initiation through project closure?

Options:

A.

Resource leveling

B.

Parametric measuring

C.

Pareto chart

D.

Earned value

Questions # 68:

Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

Options:

A.

Project Risk Management

B.

Project Integration Management

C.

Project Communications Management

D.

Project Quality Management

Questions # 69:

Which of the following techniques uses historical information to estimate the activity duration?

Options:

A.

Three-point estimating

B.

Organizational process asset

C.

Analogous estimating

D.

Reserve analysis

Questions # 70:

Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?

Options:

A.

-$8,000

B.

-$2,000

C.

$2,000

D.

$8,000

Questions # 71:

When using the Delphi technique for gathering information, what forecasting method is being used?

Options:

A.

Time series method

B.

Casual method

C.

Econometric method

D.

Judgmental method

Questions # 72:

The PV is $1000, EV is $2000 and AC is $1500. What is CPI?

Options:

A.

1.33

B.

2.00

C.

0.75

D.

0.5

Questions # 73:

Which of the following must be taken into account for every process, even if they are not explicitly listed as inputs in the process specifications?

Options:

A.

Organizational processes and procedures and enterprise environmental factors

B.

Organizational processes and procedures and corporate knowledge base

C.

Organizational process assets and enterprise environmental factors

D.

Corporate knowledge base and enterprise environmental factors

Questions # 74:

Who must accept the end product for a project to be considered closed?

Options:

A.

Project team

B.

Project manager

C.

Project management office

D.

Customer or sponsor

Questions # 75:

Which of the following methods is a project selection technique?

Options:

A.

Flowcharting

B.

Earned value

C.

Cost-benefit analysis

D.

Pareto analysis