Questions # 121:

A process that is not part of a Project Risk Management is:

Options:

A.

Identification

B.

Solicitation

C.

Quantification

D.

Response Development

Questions # 122:

Information should be communicated to __________.

Options:

A.

Everyone in the communication plan

B.

Everyone on the team

C.

Sponsor

D.

Team 'eacl

Questions # 123:

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

Options:

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

Questions # 124:

To calculate the late start and late finish dates for a set of tasks , you must do :

Options:

A.

An analysis of the critical path

B.

A forwards pass

C.

A backwards pass

D.

a and g

Questions # 125:

Which of the following is ensuring that all features and functions are included in a product or service

Options:

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope

Questions # 126:

The buyer and seller are bound by the ________.

Options:

A.

Contract

B.

Responsibilities

C.

WBS

D.

Identification

Questions # 127:

Which of the following best describes project scope?

Options:

A.

The work that must be done in order to deliver a product with the specified features and functions

B.

The description of the project deliverables

C.

The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks

D.

The process of planning and executing all of the required work to deliver the project

Questions # 128:

Analogous Estimate Costs is _________.

Options:

A.

Generally Accurate

B.

Generally less accurate

C.

Bottom-up estimating

D.

None

Questions # 129:

In which type of organization, a project manager is in complete control of the project?

Options:

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

Questions # 130:

Which process must occur after a project manager has been assigned to the project?

Options:

A.

Collect Requirements

B.

Develop the project charter

C.

Develop the project statement of work

D.

Develop project closing document

Questions # 131:

Which of the following is not part of project scope management?

Options:

A.

Verify Scope

B.

Collect Requirements

C.

Create WBS

D.

None of the above

Questions # 132:

A Trend Analysis is best described as:

Options:

A.

Examining project performance over time

B.

Calculating Earned Value

C.

Calculating Cost Variance

D.

Analyzing performance of similar projects over time

Questions # 133:

The activity that is most concerned with the current status of the project schedule is called ___________.

Options:

A.

Project time management

B.

Control Schedule

C.

Monitoring and controlling

D.

Al1 of the above

Questions # 134:

A major assumption of all network scheduling methods is that the activity duration must be _____.

Options:

A.

Statistically dependent

B.

Variance distributed

C.

Statistically independent

D.

Deterministic

Questions # 135:

Which of the following plans is not done during the writing of a project plan?

Options:

A.

Executive Communication

B.

Risk Management

C.

Quality Management

D.

Scope Statement

Viewing page 9 out of 11 pages
Viewing questions 121-135 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.