Questions # 91:

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Questions # 92:

Which technique is commonly used for the Quantitative Risk Analysis activity?

Options:

A.

Brainstorming

B.

Strategies for Opportunities

C.

Decision Tree Analysis

D.

Risk Data Quality Assessment

Questions # 93:

What do composite organizations involve?

Options:

A.

Functional and project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Questions # 94:

Which schedule development technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Questions # 95:

Which of the following is an input to identify risk?

Options:

A.

Organizational process assets

B.

Scope management plan

C.

Communication management plan

D.

Expert judgment

Questions # 96:

The Project Management Body of Knowledge (PMBOK Guide) should be considered as a:

Options:

A.

guide to project management processes, tools and techniques.

B.

methodology for managing projects.

C.

guide for project, portfolio and program management.

D.

standard for project, portfolio and program management.

Questions # 97:

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

Options:

A.

Perform periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards

D.

Complete the quality control checklist.

Questions # 98:

What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?

Options:

A.

Bottom-up estimating

B.

Analogous estimating

C.

Parametric estimating

D.

Three-point estimates

Questions # 99:

A weighting system is a tool for which area of procurement?

Options:

A.

Plan contracting

B.

Request seller responses

C.

Select sellers

D.

Plan purchase and acquisition

Questions # 100:

Which of the following choices is a contract closure tool or technique?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Questions # 101:

Which of the following will be required to perform simula-tion for schedule risk analysis?

Options:

A.

Activity list and activity attributes

B.

Schedule network diagram and duration estimates

C.

Schedule data and activity resource requirements

D.

Milestone list and resource breakdown structure

Questions # 102:

Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?

Options:

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Questions # 103:

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-Benefit Analysis

B.

Variance Analysis

C.

Reserve Analysis

D.

Stakeholder Analysis

Questions # 104:

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert Judgment

B.

Project Management Methodology

C.

Project Management Information

D.

Project Selection Methods

Questions # 105:

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Viewing page 7 out of 11 pages
Viewing questions 91-105 out of questions