Questions # 181:

Project Procurement Management includes all of the following EXCEPT:

Options:

A.

Administration

B.

Stakeholder analysis

C.

Planning

D.

Solicitation

Questions # 182:

The ability of a product to be used for different purposes at different capacities and under different conditions determines its __________.

Options:

A.

Usability

B.

Flexibility

C.

Operability

D.

Availability

Questions # 183:

A work breakdown structure is a ______.

Options:

A.

Result of the Collect Requirements process

B.

Deliverable oriented grouping of project elements that organizes and defines the total scope of the project

C.

Structure that can be used to track the project's time, cost, and quality performance against a defined baseline

D.

Valuable communications tool, but cannot be used to establish the number of required networks for Control Costs

Questions # 184:

Correspondence, contract changes, and payment requests are ___________ of contract administration.

Options:

A.

Outputs

B.

Tools

C.

Functions

D.

InPuts

Questions # 185:

Collect Requirements includes alternatives identification, which can be conducted by the common technique of

Options:

A.

Lateral thinking

B.

Value engineering

C.

Cost/benefit analysis

D.

Constraints analysis

Questions # 186:

Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?

Options:

A.

CPM

B.

PERT

C.

Schedule Simulation

D.

Path Convergence Method

Questions # 187:

All of the following statements about the project charter are correct except:

Options:

A.

It Is often an internal legal document.

B.

It identifies the project manager's authority and responsibility.

C.

It identifies management and/or customer approved scope of the project.

D.

It usually does not identify cost and time estimates.

Questions # 188:

During the execution phase, a resource is added to the project team. What effect will this have on the project?

Options:

A.

The effect cannot be determined

B.

The project duration will be shortened

C.

A scope change will be required

D.

The quality of the project will be increased

Questions # 189:

You are project manger of an existing project. You have been with your company for several years but not in the area where this project is occurring. A Project Management Plan is in place. The project has not exceeded many baseline change thresholds. The customer is not happy with the status of the project. Which of the following is the BEST initial action?

Options:

A.

Prepare a corrective action plan

B.

Conduct team-building with all stakeholders

C.

Verify the customer's needs and expectations

D.

None

Questions # 190:

A cost management plan is ______________.

Options:

A.

A plan for describing how cost variances will be managed

B.

A subsidiary element of the project charter

C.

An input to the Estimate Costs process

D.

Both A and C

Questions # 191:

The overall intentions and direction of an organization with regard to quality as formally expressed by top management is a __________.

Options:

A.

Quality Plan

B.

Quality Statement

C.

Quality Policy

D.

TQM

Questions # 192:

Which of the following is not an input into organizational planning?

Options:

A.

Recruitment practices

B.

Project interfaces

C.

Staffing requirements

D.

Constraints

Questions # 193:

A key barrier to team development is _________.

Options:

A.

A strong matrix management structure

B.

When major problems delay the project completion date or budget targets

C.

When team members are accountable to both functional and project manager!

D.

When formal training plans cannot be implemented

Questions # 194:

The BEST way to organize project activities for scheduling is by ________.

Options:

A.

WBS

B.

Critical Path

C.

Task start date

D.

Responsible organization

Questions # 195:

The belief that management's high levels of trust, confidence and commitment to workers leads to high levels of motivation and productivity on the part of workers is a part of which motivation theory?

Options:

A.

Theory Y

B.

Theory Z

C.

Theory X

D.

Contingency Theory

Viewing page 13 out of 15 pages
Viewing questions 181-195 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.