Viewing page 14 out of 15 pages
Viewing questions 196-210 out of questions
Questions # 196:

You are the project manager of a project .The senior executive of your company wants monthly schedule update of your project. Which of the following would you send to the executive?

Options:

A.

Milestone chart

B.

Time scaled network diagram

C.

Arrow activity diagram

D.

PERT chart

Questions # 197:

The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards is called __________.

Options:

A.

Quality Assurance

B.

Quality Control

C.

Plan Quality

D.

Quality Review

Questions # 198:

Which of the following is NOT considered a cost of non-conformance to quality?

Options:

A.

Scrap

B.

Rework

C.

Liabilities

D.

Training

Questions # 199:

An example of risk mitigation is:

Options:

A.

Taking early action to reduce probably of risk rather repair the damage after risk has occurred.

B.

Purchasing insurance

C.

Eliminating the cause of a risk

D.

You develop a contingency plan to execute in case the risk event occurs.

Questions # 200:

Estimate Costs_____________.

Options:

A.

Involves developing an estimate of the costs of the resources needed to complete project activities

B.

Cost estimates are generally expresses in unit of some currency.

C.

Involves allocating the overall estimates to individual work items

D.

All of the above

Questions # 201:

The ___________ documents the characteristics of the product or service that the project was undertaken to create.

Options:

A.

Project charter

B.

Scope statement

C.

Product description

D.

Technical article

Questions # 202:

Which process involves Formal product acceptance and end of project?

Options:

A.

Executing processes

B.

Planning processes

C.

Controlling Processes

D.

Closing processes

Questions # 203:

A unilateral contract under which the seller is paid a preset amount per unit of service is called __________.

Options:

A.

A cost reimbursable contract

B.

A lump sum contract

C.

A time and material contract

D.

A fixed price contract

Questions # 204:

Project Risk Management includes all of the following processes EXCEPT ________.

Options:

A.

Plan Risk Management

B.

Identify Risks

C.

Risk Analysis

D.

Plan R^ Response

Questions # 205:

Which of the following statements is false?

Options:

A.

Uncertainty and risk are greatest at the start of the project and lowest at the end.

B.

The amount at stake Is lowest at the end of the project and greatest at the start.

C.

Expected monetary value can be expressed as the product of the risk event probability and the risk event value.

D.

Opportunities are positive outcome of risks.

Questions # 206:

Projects are typically authorized as a result of any of the following except:

Options:

A.

Market demand

B.

Successful RFP bidding

C.

Regulatory requirement

D.

Technological advance

Questions # 207:

Determining conformance with scope requirements is called _________.

Options:

A.

Quality Management

B.

Quality Assurance

C.

plan Quality

D.

Quality Control

Questions # 208:

Wgich of the following is NOT considered as strategy for positive risk ?

Options:

A.

Avoid

B.

Transfer

C.

Accept

D.

ExPlot

Questions # 209:

Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?

Options:

A.

A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part.

B.

Contingency reserves may be set aside for known unknowns.

C.

Contingency reserves may be set aside for unknown unknowns.

D.

Contingency reserves are normally included in the project's cost and schedule baselines.

Questions # 210:

Which of the following contract types places the greatest risk on the seller?

Options:

A.

Cost-plus-fixed-fee contract

B.

Cost-plus-incentive-fee contract

C.

Fixed-price-incentive fee contract

D.

Firm-fixed-price contract

Viewing page 14 out of 15 pages
Viewing questions 196-210 out of questions