Questions # 41:

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?

Options:

A.

Review any reports of conflict between each of the team members over the last two years, and select only those with a track record of working well together.

B.

Ensure there is a balanced mix of people who are experts and members with broad experience based on the work to be performed and determine training needs.

C.

Ensure that none of the team members are geographically dispersed so that all team members can be colocated.

D.

Review each team member's contributions to the velocity of their previous projects and select the highest performers.

Questions # 42:

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Questions # 43:

A Scrum team has worked hard to reach their sprint goal, but impediments have prevented them from succeeding. The team needed help from a specialist on another team, but the specialist was on a 2-week vacation.

What should the scrum master do?

Options:

A.

At the sprint retrospective, the scrum master and development team should discuss why the team did not know the specialist was unavailable during the sprint. The scrum master should then set clear rules so situations like these can be avoided in the future.

B.

It can be very distressing for a Scrum team not to reach its sprint goals. The scrum master should hold an evaluation meeting to discuss who in the team was responsible for discovering the specialist was not available, then make an improvement task for the next sprint.

C.

The scrum master, as a servant leader, should always try to remain positive about the team's work. Even when team members’ make mistakes, there should be trust that everyone is doing their best. Engaged team members work more efficiently, and a sustainable pace is important for project success.

D.

At the sprint retrospective, the Scrum team should reflect on how the past sprint has worked out. The scrum master should facilitate an open discussion to discover the root causes for the missed sprint goals and find a way to avoid similar situations in future sprints.

Questions # 44:

There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story. Who should the Scrum Master invite to the meeting?

Options:

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner

Questions # 45:

A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.

What should be proposed to the team?

Options:

A.

Have other team developers attend training to learn database skills.

B.

Monitor the retrospectives of two additional sprints before taking action.

C.

Plan fewer stories for the sprint to reduce the database engineers' workload.

D.

Ask the scrum master to work with the product owner to remove backlog stories that have database dependency.

Questions # 46:

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

Options:

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.

B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.

C.

Ask the product owner to conduct these discussions in individual meetings with the team members.

D.

Remind the team that staying on topic during meetings is part of being a self-managing team.

Questions # 47:

During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal.

What practice is the agile facilitator implementing?

Options:

A.

Building openness and transparency on the project's health and status

B.

Facilitating conflict resolution among executive team members

C.

Using active stakeholder involvement to build features in an incremental and iterative approach

D.

Seeking continuous feedback from executive team members

Questions # 48:

During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Questions # 49:

The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority.

D.

Discuss the performance of the solution at the next sprint review

Questions # 50:

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team. What is the agile project leader doing?

Options:

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Viewing page 5 out of 15 pages
Viewing questions 41-50 out of questions